Your project was just completed. Due to some unfortunate circumstances, the project was delayed causing cost overruns at the end of the project. Which of the following is true?
A. You document the circumstances as lessons learned.
B. You pay particular attention to archiving the financial records for this project.
C. Your project ended due to starvation because of the cost overruns.
D. You document the circumstances surrounding the project completion during the Scope Verification process.


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

You are a project manager for Safari Outfitters. Your company is going to offer a new product line in the upcoming spring catalog. Your project team has 10 months to secure contracts with suppliers, finalize the designs, get the product into the catalog, and stock the warehouse. This is an example of: A. An assumption because the project team has worked on projects like this before and know they can meet the 10-month deadline B. An assumption because the project team has a limited amount of time to complete the project C. A constraint because the project team has a limited amount of time to complete the project D. A constraint because the project team is working with a new product line that hasn't been developed before

0 Answers  


The purpose of a quality audit includes all of the following except: A. Examines the work of the project and formally accepts the work results B. Determines how the project is progressing and makes corrections C. Identifies lessons learned D. Reviews quality management activities to ensure the right quality elements are being examined

0 Answers  


You are a project manager for a telecommunications firm. You're working on a project that entails upgrading technical hardware and equipment. The estimated cost of the hardware and equipment is $1,725,000. You are reviewing products from three different vendors. One of the vendors invites you to lunch. What is the most appropriate response? A. Thank them but let them know this could be a conflict of interest since you haven't made a decision about which vendor you're going to choose. B. Thank them and decline. You know this could be considered personal gain, which could call your integrity into question. C. Thank them and accept. You don't believe there is a conflict of interest or a personal integrity issue. D. Thank them and decline. You believe this could be a conflict of interest on the part of the vendor, and you don't want to encourage that behavior.

0 Answers  


You are the project manager for a top-secret software project for an agency of the United States Government. Your mission, should you choose to accept it, is to complete the project using internal resources. The reason is because getting top secret clearances for contractors takes quite a bit of time and waiting for clearances would jeopardize the implementation date. Your programmers are 80 percent of the way through the programming and testing work when your agency appoints a new executive director. Your programmer’s are siphoned off this project to work on the executive director's hot new project. Which of the following addresses the purpose of Scope Verification in this case? A. It determines the correctness and completion of all the work B. It documents the level and degree of completion C. It determines if the project results comply with quality standards D. It documents the correctness of the work according to stakeholders' expectations

0 Answers  


You are a project manager working for Mail House King. Your company processes orders for several mail-order catalog companies. Your project is to install new mail-sorting equipment and software. You’ve had some problems and experienced some variances so far during the project. You do not expect these variances to continue, as they're atypical. Your project sponsor has asked for an EAC. You know the following information: PV = 800, BAC = 700, EV = 675, AC = 750, and ETC = 30. Which of the following is the correct EAC given the circumstances? A. 25 B. 760 C. 775 D. 833

0 Answers  






Which of the following are the tools and techniques of the Cost Budgeting process? A. Project management information system, analogous estimating, bottom-up estimating, mathematical analysis B. Analogous estimating, bottom-up estimating, mathematical analysis, computerized tools C. Project management software, analogous estimating, bottom-up estimating, parametric modeling D. Analogous estimating, bottom-up estimating, parametric modeling, computerized tools

0 Answers  


The project schedule is used to determine all of the following except: A. Cost estimates B. Activity start dates C. Float times D. Activity end dates

0 Answers  


What will you do, if your subordinate has a problem with you? How will you deal with this situation

18 Answers   Verizon,


Your project was just completed, accepted, and closed. As is customary for your organization, you conduct a post-implementation audit. The purpose of this audit includes all of the following except: A. Evaluating project goals and comparing them to project product B. Reviewing successes and failures C. Documenting the acceptance of the work results D. Documenting possible improvements for future projects

0 Answers  


The amount of authority a project manager possesses can be related to: A. The project manager’s communication skills B. The organizational structure C. The amount of authority the manager of the project manager possesses D. The project manager's influencing skills

0 Answers  


Critical path tasks are those tasks that: A. Have equal pessimistic, optimistic, and most likely estimated times B. Have a float rime of zero C. Have the same start date D. Have multiple early start dates and early finish dates

0 Answers  


Your project involves the research and development of a new food additive. You’re ready to release the product to your customer when you discover that a minor reaction might occur in people with certain conditions. The reactions to date have been very minor, and no known long-lasting side effects have been noted. As project manager you should: A. Do nothing because the reactions are so minor that very few people will be affected. B. Inform the customer that you've discovered this condition and tell them you'll research it further to determine the impacts. C. Inform your customer that there is no problem with the additive release the product to them. D. Tell the customer you'll correct the reaction problems in the next batch but you'll release the first batch of product to them now to begin using.

0 Answers  


Categories