Your selection committee meets on a semiannual basis. They've determined that projects must meet or exceed a specific profit limit in order to be accepted and prioritized on the project list. Which of the following is true?
A. The selection committee has defined project selection criteria, which is a tool and technique of Initiation.
B. The selection committee has defined project selection methods, which is a tool and technique of Initiation.
C. The selection committee has defined project selection methods, which is an input to Initiation.
D. The selection committee has defined project selection criteria, which is an input to Initiation.
No Answer is Posted For this Question
Be the First to Post Answer
All of the following arc tools and techniques of the Project Plan execution process except: A. Project management information system B. Work authorization system C. Organizational policies D. General management skills
What is the key activity during Contract Closeout and Administrative Closure? A. Documenting lessons learned B. Creating project archives C. Disseminating information to formalize project closure D. Documenting project closure
You are a project manager working on contract with a company in a foreign country. At the project kick-off meeting, you are given an expensive-looking gift. The person who presented this to you said that it is customary in their country to give their business partners gifts. What is the most appropriate response? A. Thank them and decline. Explain that this is considered personal gain, which is unacceptable in your country. B. Thank them and accept. You don't believe there is a conflict of interest or an integrity issue at stake. C. Thank them and decline. Explain that this is considered a conflict of interest, which is unacceptable in your country. D. Thank them and accept since you know that it would be considered offensive to decline the gift in their culture. Immediately report the acceptance of the gift to the appropriate parties at your company so that your actions are not called into question later.
Each of the following describes an element of the Scope Definition process except: A. Breaking down the major deliverables of the project into smaller, manageable components B. Supporting detail C. Decomposition D. Improving the accuracy of time and cost estimates
You have been assigned to a project in which the objectives are to expand three miles of the north-south highway through your city by two lanes in each direction. You are in charge of the demolition phase of this project, and you report to the project manager in charge of this project. You have been hired on contract and will be released at the completion of the demolition phase. What type of organizational structure does this represent? A. Functional organization B. Weak matrix organization C. Projectized organization D. Balanced matrix organization
You are a project manager working on gathering requirements and establishing estimates for the project. Which process group are you in? A. Planning B. Executing C. Initiation D. Controlling
Waht is the level of criticallity in Project management for a Project which is started in maintenance Phase ? Which phase of Project management theory must be more focused for such kind of projects .
6 Answers ABB, BGR Energy, TCS,
Which of the following is true regarding the critical path? A. It should never be compressed. B. It allows for looping and branching. C. The critical path technique is the same as PERT. D. It's the duration of all tasks with zero float.
Your project is progressing as planned. The project team has comp up with a demo that the sales team will use when making presentations to perspective clients. You will do which of the following at your next stakeholder process. A. Report on the progress of the demo and note that it's a completed task B. Preview the demo for stakeholders and obtain their approval and sign-off C. Review the technical documentation of the demo and obtain approval and sign-off D. Report that the demo has been noted as a completed task in the information retrieval system
Which of the following compression techniques increases risk? A. Crashing B. Resource leveling C. Fast tracking D. Lead and lag
You are a project manager for Laurel's theater productions. Your new project is coming in over budget and requires a cost change through the cost change control system. You know all of the following are true regarding Cost Control except: A. Performance is monitored to detect variances B. Changes are reflected in the cost baseline C. Changes are monitored and reflected in the project scope D. Changes are monitored so that inappropriate changes do not get into the cost baseline
Your project was just completed, accepted, and closed. As is customary for your organization, you conduct a post-implementation audit. The purpose of this audit includes all of the following except: A. Evaluating project goals and comparing them to project product B. Reviewing successes and failures C. Documenting the acceptance of the work results D. Documenting possible improvements for future projects