Which of the following compression techniques increases risk?
A. Crashing
B. Resource leveling
C. Fast tracking
D. Lead and lag
No Answer is Posted For this Question
Be the First to Post Answer
What are the tools and techniques of the Contract Administration process? A. Contract change control system, payment system, payment requests B. Contract change control system, contract negotiations, payment system C. Contract change control system, contract negotiations, contract changes D. Contract change control system, performance reporting, payment system
Critical path tasks are those tasks that: A. Have equal pessimistic, optimistic, and most likely estimated times B. Have a float rime of zero C. Have the same start date D. Have multiple early start dates and early finish dates
Ruby is an administrative assistant with another department. Her manager has agreed to loan Ruby's services to you on a part-time basis during your current project. Ruby is putting together the cost projections you've gathered so far. You want to include these costs in the project charter. Ruby is formatting this information for you into a spreadsheet package and is printing copies. Which of the following is true? A. All of the costs, including Ruby's time, are charged to the project. B. All of the costs, Ruby is typing into the spreadsheet are project costs. Ruby's time is not directly related to the project and should not be included. C. The project costs, including Ruby's time, should be included in the project charter. D. The project costs, excluding Ruby's time, should be considered project constraints.
All of the following are tools and techniques of the Integrated Change Control process except: A. Configuration management B. Performance measurements C. Change requests D. Additional planning
You are a project manager for Uncle Sam's Flag Company. Your company has designed a new line of products featuring the American flag. Due to some unique circumstances, the products are in hot demand and the project sponsor has asked you to do whatever it takes to get this project completed early and make the products available. You are to add resources to the project. The sponsor agrees to pay the additional costs since time is now a critical factor. Which technique have you used? A. Crashing B. Resource leveling C. Fast tracking D. Resource loading
Which of the following processes negotiates the sequence of award by rank ordering the proposals? A. Source Selection B. Solicitation C. Contract Administration D. Procurement
Which of the following processes assess the likelihood of risk occurrences and their consequences using numeric probability assignments? A. Qualitative Risk Analysis B. Risk Identification C. Quantitative Risk Analysis D. Risk Response Planning
You are a project manager for Laurel's theater productions. Your new project is coming in over budget and requires a cost change through the cost change control system. You know all of the following are true regarding Cost Control except: A. Performance is monitored to detect variances B. Changes are reflected in the cost baseline C. Changes are monitored and reflected in the project scope D. Changes are monitored so that inappropriate changes do not get into the cost baseline
What is the difference between risk impact and risk probability?
Explain on the project management life cycle process?
HI everyone, I am commerce graduate, completed MBA Finance in Distinction. I would like to do FI/CO. Could any one of you please suggest, which is the best instistute for FI/CO training in Hyderabad. Compulearn, Reliance, or other. Thanks in advance Rupa Gupta
You are a project manager for a new software development project. You have a few activities that require specialized testing. The testing might need to be repeated more than once. Which of the following do you choose? A. The Graphical Evaluation and Review Technique because it allows for conditional branching and looping for the testing activity B. The Critical Path Method because it allows for float time to be calculated for the testing activity C. The Program Evaluation and Review Technique because it allows for conditional branching and looping for the testing activity D. The Program Evaluation and Review Technique because it allows for a weighted average distribution, which will even out the time needed for the testing activity