You have been assigned to a project in which the objectives are to expand three miles of the north-south highway through your city by two lanes in each direction. You are in charge of the demolition phase of this project, and you report to the project manager in charge of this project. You have been hired on contract and will be released at the completion of the demolition phase. What type of organizational structure does this represent?
A. Functional organization
B. Weak matrix organization
C. Projectized organization
D. Balanced matrix organization


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

Which of the following is true regarding NPV? A. NPV assumes reinvestment at the cost of capital. B. NPV decisions should be made based on the highest value for all of the selections. C. NPV assumes reinvestment at the prevailing rate. D.NPV assumes reinvestment at the NPV rate.

0 Answers  


what kind of questions can be asked from SDLC for a project leader role?

1 Answers   Satyam, TCS,


You are the project manager for an outdoor concert event scheduled for 1 year from today. You're working on the procurement plan for the computer software program that will control the lighting and screen projections during the concert. You've decided to contract with a professional services company that specializes in writing custom software programs. You want to minimize the risk to the organization, so you'll option for which contract type? A. Fixed price plus incentive B. Cost plus fixed fee C. Fixed price D. Cost plus incentive

0 Answers  


As project manager, you know that all of the following are true concerning analogous estimating techniques except: A. It's a qualitatively based estimating technique. B. It's a top-down estimating technique. C. It's a tool and technique of Activity Duration Estimating and Cost Estimating. D. It’s a form of expert judgment.

0 Answers  


What is the name of the unplanned response used to deal with negative risk events in the Risk Monitoring and Control process? A. Mitigation B. Contingency plans C. Workarounds D. Corrective action

0 Answers  






During a recent team meeting, you reached a resolution to a problem that's been troubling the team for several weeks. You took responsibility for searching out the facts of this problem and uncovered the right answer to this problem. You presented the facts at the project status meeting, and everyone reached agreement on the recommended solution based on the facts you presented. This is an example of what type of conflict resolution technique? A. Compromise B. Smoothing C. Confrontation D. Forcing

0 Answers  


You are the project manager working on a research project for a new drug treatment. Your preliminary project schedule runs past the due date for a federal grant application. You adjust the schedule and find that two activities previously scheduled to start sequentially can be started at the same time. This is an example of: A. Crashing B. Fast tracking C. Resource leveling D. Adjusting the resource calendar

0 Answers  


Three people are responsible for establishing cost of quality theories. Crosby and Juran are two of them, and their theories respectively are: A. Grades of quality, fitness for use B. Fitness for use, zero defects C. Zero defects, fitness for use D. Cost of quality, zero defects

0 Answers  


Your project has recently experienced change. Some of the agreed-upon WBS elements have been changed as a result. What kind of change has occurred? A. Schedule change B. Risk response change C. Quality change D. Scope change

0 Answers  


explain the contents of menubar

1 Answers   Wipro,


You are a project manager for Waterways Houseboats, Inc. You have been asked to perform a benefit/cost analysis for two proposed projects. Project A costs $2.4 million with potential benefits of $12 million and future operating cost of $3 million. Project B costs $2.8 million with potential benefits of $14 million and future operating costs of $2 million. Which project should you recommend? A. Project A because the cost to implement is cheaper than Project B B. Project A because the potential benefits plus the future operating costs are less in value than the same calculation for Project B C. Project B because the potential benefits minus the implementation and future operating costs are greater in value than the same calculation for Project A D. Project B because the potential benefits minus the costs to implement are greater in value than the same calculation for Project A

0 Answers  


Which Company in India is best for Mobile Application Development?

2 Answers  


Categories