What is one of the most important skills a project manager can have?

A. Negotiation skills
B. Influencing skills
C. Communication skills
D. Problem-solving skills


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

You are a project manager for Picture Shades, Inc. They manufacture window shades for hotel chains that have replicas of Renaissance-era paintings on the inside of the shades. Picture Shades is taking their product to the home market, and you're managing the new project. They will offer their products at retail stores as well as on their website. You're developing the project schedule for this undertaking and have determined the critical path. Which of the following is true? A. You calculated the most likely start date and most likely finish dates, float time, and weighted average estimates. B. You calculated the activity dependency, and the optimistic and pessimistic activity duration estimates. C. You calculated the early and late start dates, early and late finish dates, and float times for all activities. D. You calculated the optimistic, pessimistic, and most likely duration times and the float times for all activities.

0 Answers  


The purpose of a quality audit includes all of the following except: A. Examines the work of the project and formally accepts the work results B. Determines how the project is progressing and makes corrections C. Identifies lessons learned D. Reviews quality management activities to ensure the right quality elements are being examined

0 Answers  


You are the project manager for your company's annual Spring Fling. You've made all the plans and reserved the outdoor grounds for the appropriate day and time. You are now two days away from the big day, and the forecast is calling for light rain showers in the afternoon. You rented tents just in case this risk occurred. This is an example of which Risk Response Planning tool and technique? A. Passive acceptance B. Contingency planning C. Avoidance D. Transference

0 Answers  


Procurement audits review what? A. The procurement process from Procurement Planning through Contract Administration B. The contract administration process from Solicitation Planning through Contract Administration C. The procurement process from Procurement Planning through Contract Closeout D. The contract administration process from Solicitation Planning through Contract Closeout

0 Answers  


You are the project manager for a custom home-building construction company. You are working on the model home project for the upcoming Show Homes Tour. The model home includes Internet connections in every room and talking appliances. You are working on the cost budget for this project. Which of the following is true? A. This process assigns cost estimates to project activities including risks and contingency plans. B. The cost baseline will be used to measure variances and future project performance. C. This process assigns cost estimates for expected future period operating costs. D. The cost baseline is the expected cost for the project.

0 Answers  






You are a project manager for Move It Now trucking company. Your company specializes in moving household goods across the city or across the country. Your project involves upgrading the nationwide computer network for the company. Your lead engineer has given you the following estimates for a critical path activity: 60 days most likely, 72 days pessimistic, 48 days optimistic. What is the expected value, or weighted average? A. 54 B. 66 C. 60 D. 30

0 Answers  


When a project is being performed under contract, the product description is provided by which of the following? A. The buyer B. The project sponsor C. The project manager D. The contractor

0 Answers  


You are a project manager for Bluebird Technologies. Bluebird writes custom billing applications for several industries. A scope change has been requested. You know change is concerned with all of the following except: A. Managing change B. Verifying change C. Influencing causes of change D. Determining that a change occurred

0 Answers  


What is your management Style

8 Answers   ABC, Hospitality, Thomson,


You have been assigned to a project in which the objectives are to expand three miles of the north-south highway through your city by two lanes in each direction. You are interested in implementing a new project process called design-build in order to speed up the project schedule. The idea is that the construction team will work on the first mile of the highway reconstruction. At the same lime, the design team is coming up with plans for the third mile of the reconstruction rather than completing all design before any construction begins. This is an example of: A. Managing the projects as a program B. Fast tracking C. Progressive elaboration D. Collocation

0 Answers  


What limits the options of the project team? A. Technology B. Constraints C. Deliverables D. Assumptions

0 Answers  


You are a project manager working in a foreign country. You observe that some of your project team members are having a difficult time adjusting to the new culture. You provided them training on cultural differences and the customs of this country before arriving, but they still seem uncomfortable and disoriented. Which of the following is true? A. This is the result of working with teams of people from two different countries. B. This condition is known as culture shock. C. This is the result of jet lag and travel fatigue. D. This condition is known as global culturalism.

0 Answers  


Categories