Which of the following is true regarding NPV?
A. NPV assumes reinvestment at the cost of capital.
B. NPV decisions should be made based on the highest value for all of the selections.
C. NPV assumes reinvestment at the prevailing rate.
D.NPV assumes reinvestment at the NPV rate.
No Answer is Posted For this Question
Be the First to Post Answer
Your company has asked you to be the project manager for the product introduction of their new DeskTop Rock media system. You recently published a document that establishes the scope baseline. Which of the following is true? A. This is the scope statement, which is an output of the Scope Planning process. B. This is the scope statement, which is an output of the Scope Definition process. C. This is the scope statement, which is a tool and technique of the Scope Definition process. D. This is the scope management plan, which is an output of the Scope Definition process.
What are the outputs of the Team Development process? A. Performance improvements, input to performance appraisals B. Input to performance appraisals, reward and recognition systems C. Performance improvements, input to performance appraisals, performance reports D. Work results, input to performance appraisals, performance reports
All of the following describe the activity list except: A. It's an extension of the WBS. B. It includes all activities of the project. C. It describes the WBS updates. D. It includes a description of project activities.
As a project manager, you're responsible for maintaining and ensuring integrity for all of the following except: A. Personal integrity of others B. Project management process C. Personal integrity D. Product integrity
Many times software delivery is late, why? Give reason.
You've constructed the WBS for your recent project. Level two assignments have been made, and you've requested that the sub project manager’s report back to you in 3 weeks with each of their individual WBS constructed. All of the following are true except: A. The work package level facilitates resource assignments. B. The work package level is the lowest level in the WBS. C. The work package level defines the agreed-upon deliverables. D. The work package level facilitates cost and time estimates. ?
Which organization has set the de facto standards for project management techniques? A. PMBOK B. PMO C. PMI D. PMA
Your project depends on a key deliverable from a vendor you've used several times before with great success. You're counting on the delivery to arrive on June 1. This is an example of : A. Constraint B. Objective C. Assumption D. Goal
what is software project planning?
You know that PV = 475, AC = 430, EV = 480, EAC = 40, and BAC = 525. What is VAC? A. 440 B. 390 C. 485 D. 435
Ruby is an administrative assistant with another department. Her manager has agreed to loan Ruby's services to you on a part-time basis during your current project. Ruby is putting together the cost projections you've gathered so far. You want to include these costs in the project charter. Ruby is formatting this information for you into a spreadsheet package and is printing copies. Which of the following is true? A. All of the costs, including Ruby's time, are charged to the project. B. All of the costs, Ruby is typing into the spreadsheet are project costs. Ruby's time is not directly related to the project and should not be included. C. The project costs, including Ruby's time, should be included in the project charter. D. The project costs, excluding Ruby's time, should be considered project constraints.
You have been assigned to a project in which the objectives are to expand three miles of the north-south highway through your city by two lanes in each direction. You are interested in implementing a new project process called design-build in order to speed up the project schedule. The idea is that the construction team will work on the first mile of the highway reconstruction. At the same lime, the design team is coming up with plans for the third mile of the reconstruction rather than completing all design before any construction begins. This is an example of: A. Managing the projects as a program B. Fast tracking C. Progressive elaboration D. Collocation