All of the following are true about decomposition except:
A. It's an output of the Scope Definition process.
B. It's a tool and technique of the Scope Definition process.
C. It is used to create a WBS.
D. It subdivides the major deliverables into smaller components.
No Answer is Posted For this Question
Be the First to Post Answer
You are the project manager for Heart of Texas casual clothing company. Your project involves installing a new human resources system. You've identified the risks associated with this project and are ready for the next step. What is the next step? A. You will evaluate the risks and assign probabilities and impacts using Qualitative and/or Quantitative Risk Analysis. B. You will use the Delphi technique to confirm the risks you've detailed and identify others you may have missed. C. You must evaluate the risks and assign probabilities and impacts using both Qualitative Risk Analysis, which comes first, then Quantitative Risk Analysis. D. You will define the steps to take to respond to the risks and detail them in the risk response plan.
The lowest level of the WBS is called what? A. Code of accounts B. Requirement C. Milestone D. Work package
You are a project manager for Dakota Software Consulting Services. You're working with a major retailer that offers their products through mail-order catalogs. They're interested in knowing customer characteristics, the amounts of first-time orders, and similar information. As a potential bidder for this project, you worked on the RFP response and submitted the proposal. When the selection committee received the RFP responses from all the vendors bidding on this project, they used a weighted system to make a selection. Which process did this occur in? A. Source Selection B. Solicitation C. Requisition D. Contract Administration
The Project which is handled by you is in RED, customer has given you 4 weeks to show improvement, still nothing has worked out. The Customer again gives 3 weeks to improve and you do your best to improve, but nothing works out. Now the customer is not at all happy, HOW TO CONVINCE THIS CUSTOMER ???
8 Answers AZS, BGR Energy, Wipro,
You are the project manger for Xylophone Phonics. They produce children's software programs that teach basic reading and math skills. You are ready to assign project roles, responsibilities, and reporting relationships. Which project Planning process are you working on? A. Resource Planning B. Organizational Planning C. Staff Acquisition D. Human Resource Acquisition
You do not expect the types of variances that have occurred on the project to date to continue. If BAC = 300, ETC = 275, PV= 300, AC = 200, EV = 250, and CPI = 1.25, what is the EAC? A. 240 B. 250 C. 475 D. 150
You are a project manager for Capella Systems. Your company writes custom software for accounting and financial systems for medium- to large-sized corporations. Your recent project has experienced some setbacks, and you've been forced to rework the design of one of the programs because it doesn't match the customer's requirements. Since some parts of the program have already been written, it will have to be rewritten so that it matches the design changes. This rework has increased costs, and you're beginning to notice some signs of poor morale because of the rework. Which of the following is true? A. The problems occurred because the WBS was not constructed properly. B. The quality assurance plan was carried out correctly, which is how the design problems were discovered. C. The problems occurred as a result of poor scope definition. D. The Risk Management Planning process details these kinds of risks and the responses you should put into place should they occur.
You've constructed the WBS for your recent project. Level two assignments have been made, and you've requested that the sub project manager’s report back to you in 3 weeks with each of their individual WBS constructed. All of the following are true except: A. The work package level facilitates resource assignments. B. The work package level is the lowest level in the WBS. C. The work package level defines the agreed-upon deliverables. D. The work package level facilitates cost and time estimates. ?
You are a fabulous project manager, and your team thinks highly of you. You are well respected by the stakeholders, management ream, and project team. When you make decisions, others follow your lead as a result of which of the following? A. Referent power B. Expert power C. Legitimate power D. Punishment power
What are the qualities of a good project manager?
You’ve been assigned as a project manager on a research and development project for a new dental procedure. You’ve published the scope statement and are working on the scope management plan. What is the purpose of the scope management plan? A. It describes and documents a scope baseline to help make future project decisions. B. It decomposes project deliverables. C. It describes how project scope changes will be incorporated into the project and how project scope will be managed. D. It describes how cost and time estimates can be composed for project scope changes.
You are constructing a probability/impact risk rating matrix for your project. Which of the following is true? A. The PI matrix multiplies the risk's probability by the cost of the impact to determine an expected value of the risk event. B. The PI matrix multiplies the risk's probability scales, which fall between 0.0 and 1.0, and the risk’s impact scales to determine a risk score. C. The PI matrix multiplies the risk's probability by the expected value of the risk event to determine the risk impact and assign a risk score based on a predetermined threshold. D. The PI matrix multiplies the risk's probability scales and the risk's impact scales, which fall between 0.0 and 1.0, to determine a risk