All of the following are true regarding configuration management except:
A. Requires all acceptance decisions to be made through the CCB
B. Serves as a change control system
C. Describes the physical characteristics of the product of the project
D. Controls changes to the characteristics of an item or system


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

All of the following are tools and techniques of the Schedule Development process except? A. CPM B. RAM C. GERT D. PERT

0 Answers  


You’re promised your team two days of paid time off plus a week’s training in the latest technology of their choice if they complete their project ahead of schedule. This is an example of which of the following? A. Achievement theory B. Expectancy theory C. Maslow's theory D. Contingency theory

0 Answers  


You are a project manager for Laurel's theater productions. Your new project is coming in over budget and requires a cost change through the cost change control system. You know all of the following are true regarding Cost Control except: A. Performance is monitored to detect variances B. Changes are reflected in the cost baseline C. Changes are monitored and reflected in the project scope D. Changes are monitored so that inappropriate changes do not get into the cost baseline

0 Answers  


You know that BAC = 375, PV = 300, AC = 200, and EV = 250. Variances that have occurred on the project to date are not expected to continue. What is the ETC? A. 75 B. 50 C. 125 D. 150

0 Answers  


Which of the following is true regarding IRR? A. IRR assumes reinvestment at the cost of capital. B. IRR is the discount rate when NPV is greater than zero. C. IRR is a constrained optimization method. D. IRR is the discount rate when NPV is equal to zero. ?

0 Answers  






The grouping of project elements by deliverables is known as what? A. The code of accounts B. The work package C. The work breakdown structure D. The work breakdown dictionary

0 Answers  


Which of the following are the outputs of the Contract Closeout process? A. Project archives, formal acceptance and closure, contract file B. Contract file, formal acceptance and closure C. Project archives, contract file D. Contract file, formal acceptance and closure, lessons learned

0 Answers  


What is your leadership style?

1 Answers   State Bank Of India SBI,


During contract negotiations, your vendor tells you that the equipment originally bid in the RFP is no longer available. They say the best solution is to buy the new equipment they're offering, which is a higher price than the original equipment. You have concerns that the new equipment might not be compatible with existing equipment and try to discuss this with them. They remind you that this decision was already made during the last contract negotiation meeting so there's no need to continue to discuss it. This is an example of which of the following? A. Proposal B. Compromise C. Storming D. Fair accomplish

0 Answers  


What limits the options of the project team? A. Technology B. Constraints C. Deliverables D. Assumptions

0 Answers  


The product description, strategic plan, project selection criteria, and historical information are considered: A. Inputs to the project Planning process B. Inputs to the project Overview process C. Inputs to the project Initiation process D. Inputs to the project Execution process

0 Answers  


You are a project manager for Uncle Sam's Flag Company. Your company has designed a new line of products featuring the American flag. Due to some unique circumstances, the products are in hot demand and the project sponsor has asked you to do whatever it takes to get this project completed early and make the products available. You regularly check the progress of the project with your team members using which of the following techniques? A. E-mail communication B. Status review meetings C. Project management information systems D. Receiver communication model

0 Answers  


Categories