You are a project manager for Dutch Harbor Consulting. Your latest project involved the upgrade of an organization's operating system on 236 servers. You performed this project under contract. You are in the Contract Closeout process and know that you should document:
A. Lessons learned
B. Performance measurements
C. Formal acceptance
D. Product verification
No Answer is Posted For this Question
Be the First to Post Answer
What do you mean by business object,condition object and costomising object?
All of the following are true regarding the Executing processes except: A. Executing has one core process. B. The majority of the project budget is spent here. C. The greatest conflicts are schedule conflicts. D. Project performance is measured to identify variances.
Your project was just completed. Due to some unfortunate circumstances, the project was delayed causing cost overruns at the end of the project. Which of the following is true? A. You document the circumstances as lessons learned. B. You pay particular attention to archiving the financial records for this project. C. Your project ended due to starvation because of the cost overruns. D. You document the circumstances surrounding the project completion during the Scope Verification process.
You are the project manager working on a research project for a new drug treatment. Your preliminary project schedule runs past the due date for a federal grant application. You adjust the schedule and find that two activities previously scheduled to start sequentially can be started at the same time. This is an example of: A. Crashing B. Fast tracking C. Resource leveling D. Adjusting the resource calendar
Your company provides answering services for several major catalog retailers. The number of calls coming into the service center per month has continued to increase over the past 18 months. The phone system is approaching the maximum load limits and needs to be upgraded. You've been assigned to head up the upgrade project. Based on the company's experience with the vendor who worked on the last phone upgrade project, you're confident they'll be able to assist you with this project as well. Which of the following is true? A. You’ve made an assumption about vendor availability and expertise. The project came about due to a business need. B. Vendor availability and expertise are constraints. The project came about due to a business need. C. You've made an assumption about vendor availability and expertise. The project came about due to a marketing demand. D. Vendor availability and expertise are constraints. The project came about due to a marketing demand.
You need to convey some very complex, detailed information to the project stakeholders. The best method of communicating this kind of information is? A. Verbal B. Vertical C. Horizontal D. Written
what is the use of computer in project management system ?
Comparative methods, scoring methods, and economic and cash flow analysis are all part of which of the following? A. Benefit measurement methods, which are a tool and technique in Initiation B. Constrained optimization methods, which are a tool and technique C. Benefit measurement methods, which are an input to Initiation D. Decision models, which are an output of Initiation
What is the difference between risk impact and risk probability?
You are developing your project schedule and have decided to use the PERT method to determine project duration. The estimates you've gathered so far include the following: Most likely is 200 hours, optimistic is 180 hours, and pessimistic is 220 hours. Which of the following is the correct PERT estimate? A. 190 B. 266 C. 200 D. 210
How do you set goals for your team?
Describe capability maturity model (cmm).