Project at andheri west mumbai total area of 116000 sq ft near by..Please help me out for quotation plan is ready basic details are with me , please help me out .I will mail u in autocad also.
Answer Posted / arbaz shaikh
16922sq ft=basement,
32022sq ft=super structure rehab
69087sq ft= for sale structure
Scope of work-rcc work,brick(siporex)block work,plaster.
Concrete(m-25 to m-50) -1.25cft.Sqft of bua,(for super structure.
4cft sqft of bua (for basement)
Consumption of steel(fe 550d) -5.5 kg sqft of bua for super structure.
12 kg sqft of bua for basement
What should quotation for this please guyz help me out .?
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
How to calculate the weight of sand am 20mm course aggregate in 1 c.m M25 concrete Which use 400 kg of cement ?
What happens when water mixed with cowdung is used for priming instead of water for lifting water in pumps?
how can can column be corrected when the design is not safe ? is the increasing the clearcover a solution?
what will happen if one could not properly follow the spacing of slab reinforcement bar?
what should be RCC material i.e iron rod(mm)x cement x stone x sand for laying of slab L 42'x B 22'x tk 0.375ft = 1nos & column of H 17'x15"x8" 2nos.
material used for mendrel use to bend epoxy coated rebar
how much to get of BRC lapping in full yield and half yield ?
1) What is meant by C-soil in geotechnical Engineering? 2) What is Eve board? 3) What will happen when heat is applied to cement? 4) what do you understand by the lateral dimention ?
I have a slab of 20cm thickness of 20m by 4m in wich we are installing 15 tons electric panels , and we have put 4 H-shaped columns under the slab but we have done many cores in the slab which seems very normal , can you help me by telling me how to calculate the bearing capacity of the slab or give me an idea if i should increase more columns Note: load distribution area 12*1.5 m2
how much st. steel is required for staging of concourse slab of a elevated metro station allowing through traffic .
Why should appointment store person for project ? what is the benefits for company ?
Which is the latest version of solidsworks?
pls send me interview question paper with answer of EIL/AAI/UPSC/RPSC because i am doing prepration of compitation exam of UPSC for the Asst. Executive Engineer
Define line type?
what is anchorage length,lap length and (dont remember the last one)