Answer / naveen
Total weight of water/total weight of cement*100
For exp- 400 kg uses of cement 1 m3 water cement ratio is .4 =.4*400=160 kg water
160/400*100
Is This Answer Correct ? | 1 Yes | 1 No |
calculate if the size of the beam is 300*500 then L for the top & bottom bar
SAND AND STONE AGGREGATES WASTAGE PERCENTAGE IN CONCRETING WORK?
Why M15 is replaced by M20 when ammendment are made in IS456 in 2000?
primary treatment of sewagw consist of removal of floating materials removal of sand & grit removal of organic materials all above
what is minimum steel area required for rcc slab
Suggest how many column, beem, etc required for 30 mtrs x 21 mtrs width x 8mtrs height for industrial shed of ground floor. I want to know the quantity of tmt steel consumption and Concrete consumption for budgeting
0 Answers Vishal Pipeline And Engineering,
What is the software used in civil engineering?
Types of column foundation and how to calculate its steel quantity.
what is the cutting length of 90 degree bend in four corner ring in column of 8mm dia size of column 450mmx250mm of clear cover 20mm?
13 Answers Abhiram Infra Projects, Al-Darwish, Sobha Developers,
What is the standard rate of installing ties for column(60cmx60cm) and beams(50x850)(weight)
1.what is the main responsibilites of Site Engineer ? and what are main attitude ?
Specific gravity of Cement? Water?