What is difference between load bearing structure and frame bearing structure ?
Answers were Sorted based on User's Feedback
Answer / harsh rathod
In Load bearing structure load is directly transfer to the foundation. When in frame bearing structure load is transfer to beam to column in from uper story to lower story then finnaly load is indirectly transfer to foundation.
| Is This Answer Correct ? | 10 Yes | 0 No |
the load should be transferred from slab to beam and beam to column and colum to footing it is framed structure. but the bearing structure load transferred from slab to wall and wall to earth
| Is This Answer Correct ? | 4 Yes | 1 No |
for 16mm thick cement plastring 1:6 on 100 Sq.m.New brick work,the quantity of cement required is.
how many liters of water required for 1cu.m concrete?
what are the volumes of soil stabilization mix of cement,lime and sand in the ratio of 1:1:10 respectively in 1m3?
silt%= silt volume/ silt+sand volume is this right?
whou haat goals do you have in your career
what is silica fumes or micro silica? and whr is it used? wat r its advantages?
How many times one TMT bars bents & straight upto not broken the bar.
How to do rate analysis for concrete work including shuttering work?
0 Answers DBM, Techno Solutions,
Respected Sir, I am from a hilly place called Darjeeling ,I have constructed house of 9 column out of which 4 of the column is under water , i have put rcc slab on top and on top of the rcc slab i have construced two room house with bricks and light roof , now i am planning to change the light roof with rcc slab for the two room, my main concern is will the column under water will hold the load of the new rcc slab coz it already 10 to 12 yrs old , i dont know what to do , can u advice me regarding this matter, weather to leave the upper floor roof light or make it rcc slab.(If i put the slab , it will require 45bags of cement and u calculate how much of steel and sand and pebbles) thanks with regard Anand
how to calculate the required qantities of cement, Sand and aggrigate to prepare 1 Cum of concrete mix 1:2:4
What happens when,in Prestressed girder the HDPE duct and cone size is provided more than required? (technical answer expected)
how to calculate steel for beam of simple home and for heavy buliding ? explain me briefly
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)