how to estimate plastering quantity if the given object is in circular. 12 mm thick both side 1:3
example= i have 8.15 m2 how to estimate quantity
Answers were Sorted based on User's Feedback
Answer / sreejith
I will give the basic for calculating the plastering quantity for 100 m2.You can use the same way based on your required mortar volume
Let Area to be plastered=100 m^2
& Thickness of plaster= 12mm=(12/1000)m= 0.012m
Volume of mortar required= 100 x 0.012= 1.20 m^3
Add 20% extra mortar for filling joint,depressions and
wastage.
Volume of the mortar= [0.20 X 1.20]+ 1.20=1.44 m^3
[Wet Volume]
Increase further by One-third of the volume to get Dry
volume
Quantity becomes= [(1/3) X 1.44]+ 1.44=1.92 m^3
Summation of proportion=1+5=6
For 12mm plastering in 1:5 cement:sand mortar mix,
1)Cement required= 1.92/6= 0.32 cu. m
No. of bags of cement= 0.320/0.0347=9.22 bags
>>9 bags(say)
Kgs of cement required=9 x 50= 450 kg (approx)
2)Sand required= [1.92 x (5/6)]= 1.60 cu. m
[Weight of 1 bag of cement= 50 kg
Cement should be always measured by weight to avoid
variation.
One 50 kg bag of cement weighs 1440 kg/cu. m
Volume of 1 bag of cement= 50/1440=0.0347 cu. m ]
Therefore to convert Cu. m into No of bags of 50 kg
cement,just divide the volume of cement by 0.0347
| Is This Answer Correct ? | 5 Yes | 0 No |
Answer / ajay patel
first find perimeter of cylinder that is (3.14 * D)
then multiplied by height of cylinder
do same for both side
you will ger ans in square meter
| Is This Answer Correct ? | 4 Yes | 1 No |
Answer / hanamareddy maddur
01) volume of plaster=area of plaster*thickness of plaster=8.15*.012=.0978 m2
02) 20 % extra for joint filling &wastage=.0978*.2+.0978=.117m2
03) 1/3rd volume increase to get the dry volume=1/3*.117+.117=.156m2
04) sum of proportion-1:3(1+3)=4
05) cement qty=cement proportion*volume of mortar /sum of proportion
06) cement qty=1/4*.156=.039*28.2=1.1 bag
07) sand qty=sand proportion*volume of mortar/sum of proportion
08) sand qty=3/4*.156=.12m3
| Is This Answer Correct ? | 0 Yes | 0 No |
What is pre-stressed concrete?
What is the minimum depth of a slab?
I'm constructing my house, now at lintel level. I need belt concrete with laft..length - 22ft, berth- 11ft, one side laft for 2ft, *22ft length. Kindly inform me centring cost only, without material cost.
structural engineering based
How to calculate crank length? How to calculate hook length?
In beam where lapping is allowed for top and bottom bars?
1 Answers IOCL, JMC, JMC Projects,
Mention different types of roof systems?
What happens to Load at yielding ?
explain water proofing in toilets and terrace
plz tell me the compresive stength of genral con. & foam con. all grade after 7,14,21,28 day
what is the use of dowels rod..?
Are you interested in starting a fly ash brick making unit?
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)