how to estimate plastering quantity if the given object is in circular. 12 mm thick both side 1:3
example= i have 8.15 m2 how to estimate quantity
Answer Posted / sreejith
I will give the basic for calculating the plastering quantity for 100 m2.You can use the same way based on your required mortar volume
Let Area to be plastered=100 m^2
& Thickness of plaster= 12mm=(12/1000)m= 0.012m
Volume of mortar required= 100 x 0.012= 1.20 m^3
Add 20% extra mortar for filling joint,depressions and
wastage.
Volume of the mortar= [0.20 X 1.20]+ 1.20=1.44 m^3
[Wet Volume]
Increase further by One-third of the volume to get Dry
volume
Quantity becomes= [(1/3) X 1.44]+ 1.44=1.92 m^3
Summation of proportion=1+5=6
For 12mm plastering in 1:5 cement:sand mortar mix,
1)Cement required= 1.92/6= 0.32 cu. m
No. of bags of cement= 0.320/0.0347=9.22 bags
>>9 bags(say)
Kgs of cement required=9 x 50= 450 kg (approx)
2)Sand required= [1.92 x (5/6)]= 1.60 cu. m
[Weight of 1 bag of cement= 50 kg
Cement should be always measured by weight to avoid
variation.
One 50 kg bag of cement weighs 1440 kg/cu. m
Volume of 1 bag of cement= 50/1440=0.0347 cu. m ]
Therefore to convert Cu. m into No of bags of 50 kg
cement,just divide the volume of cement by 0.0347
| Is This Answer Correct ? | 5 Yes | 0 No |
Post New Answer View All Answers
what is stressing
For sloping slabs or sloping beams why the tension steel from either side of ridge is taken into compression zone of other side?
I am doing a engineering contract with GOI. I have purchased certain material from outside Maharashtra and paid CST on that material @ 5.25%. Please intimate whether I will be liable for VAT or VAT on works contract or not.
What is the ratio of grades m5, m7.5, m10, m15, m20, m25, m30, m35, m40?
Normally in slabs, steel quantity is not added when you calculating concrete quantity for that slab, why it is not added ?
We are into industrial flooring (epoxy flooring) business. We buy material from manufacturers.We supply and laying the to companies. In our billing what tax/ taxes to be claimed from companies? Are we applicable for only WCT or any else?
How can explode a block?
how much of quantity of material required for execution of one cubic meter of random rubble masonry in 1:3 cement mortar
how to decide the mortar ratio 1:4,1:6 in masonry? same in plaster 1:3 and 1:4? which code or any document reference taken to define proportion?
calculate the quantity of cement ,sand,bars and aggregate used for 28*4 ft with 4 inch (125mm) thick
please send latest placement papers of hpcl officers trainee test. i will be very thankful to you.
What is binding spacing of the rebars at lapping zones.
"Gates of the dams are generally designed of curved shape". Why?
How much quantity of cement and sand required for the inlining of 610mm dia MS pipe 8.7mm thk.Inlining thickness is 10mm and CM ratio is 1:1.5.
how to convert cement, sand aggregate quantity from M3 to kg with full description?