how to estimate plastering quantity if the given object is in circular. 12 mm thick both side 1:3
example= i have 8.15 m2 how to estimate quantity
Answer Posted / hanamareddy maddur
01) volume of plaster=area of plaster*thickness of plaster=8.15*.012=.0978 m2
02) 20 % extra for joint filling &wastage=.0978*.2+.0978=.117m2
03) 1/3rd volume increase to get the dry volume=1/3*.117+.117=.156m2
04) sum of proportion-1:3(1+3)=4
05) cement qty=cement proportion*volume of mortar /sum of proportion
06) cement qty=1/4*.156=.039*28.2=1.1 bag
07) sand qty=sand proportion*volume of mortar/sum of proportion
08) sand qty=3/4*.156=.12m3
Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
What is the requirement for over all CG of DG from the foundation surface to absorb the vibration of heavy set.
What are the phases inspections are done by local authority while construction?
what is the dimensions of river sand truck trailer or trolly ?
what is the percentage of silt in black cotton soil.?
What is the method of soil replacement test?
Explain what is Critical Path Method (C.P.M)?
How many cum of 9.5mm stone in 1 ton ?
que.is ideal size of bricnk use in india,joint size of mortar in massinary ,how many bricks used in 1cum.how to test at site.what is the possition of marka used in bricks?
Please send me the qunty. of mason/labour required in each day for different type of civil construction work?please send me ans. in my mail.my mail id is (parthamitra086@gmail.com) or here.
How to Calculate Materials Required for PCC 1:4:8 for 1Cum & Brickwork 1:4 for 1Cum & Plastering 1:4 (15mm Thick) for 100Sqm & RCC 1:4:8 & 2mt ( L1=1mt & L2=1mt ) length of 12mm Steel bended in 90degrees what is the formula to calculate Weight & Actual Length ?
What is meant by cartesian coordinate system?
what r you reqired for concrete baching plant?
Exterior Joints,define
what is parametre for M25 after 7 days strength
what is the types of surveying?which type of survey carrying for type of work?