Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


How to calculate the quantity of brick or mortar in m3.
like in 1m3 brick =....no.
.......mortar=....m3



How to calculate the quantity of brick or mortar in m3. like in 1m3 brick =....no. .......mor..

Answer / sudar

The size of the modular brick is 190 X 90 X 90
Mortar Thickness is 10mm
Assume required brickwork volume is 1 cubic metre (m3)
Volume of bricks with mortar
Volume of 1 brick with mortar = 200 X 100 X 100 ( 10 mm mortar thickness on all sides)

= 0.2 X 0.1 X 0.1

Volume of brick with mortar = 0.002 Cum (m3)

Therefore, Number of bricks required for 1 cubic metre = 1/0.002 = 500 No.s

Volume of bricks without mortar

Volume of 1 brick without mortar = 190 X 90 X 90

= 0.19 X 0.09 X 0.09

Volume of 1 brick without mortar = 0.001539 Cum (m3)

Volume of 500 bricks without mortar = 500 X 0.001539 Cum

Volume of bricks without mortar for 1 cum = 0.7695 Cum (m3)

Therefore,

Required amount of cement mortar = 1 Cum – Volume of bricks without mortar

= 1 – 0.7695

Required amount of cement mortar = 0.2305 Cum (m3) (Wet Condition)
Dry volume of a mortar = 0.2305 cum X 1.33 = 0.306565 cum
We Assume the mortar ratio is 1:6 (1 part Cement & 6 Part Sand = 7 Part)
Required amount Cement quantity in brickwork = 0.306565 X 1/7 X 1440 kg
Required amount Cement quantity = 63 Kg = 1.26 bags (50 Kg bag)
Required amount of Sand = 0.306565 X 6/7 = 0.26277 Cubic metre (m3)

Therefore, For 1 cum of brickwork, we need

500 Numbers of bricks
63 kg of cement
0.263 m3 of sand.

Is This Answer Correct ?    0 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

how to frame the sentence in voucher pad ? Description : 1.Food Expenses during site visit 2.Stamp Paper approval expenses 3.Travelling expenses 4. sweet distribution

0 Answers   L&T, Voltas,


I am in India. Employer A got approval for my H1. But they have no job for me now. Company B is going to file H1 for me. They do not know about company A. Is there any way that I get approved H1 of company A transferred to Company B?

0 Answers  


why should we use 20mm graded metal only in vrcc?why we shouldnot use 40mm metal?

2 Answers  


how many kg of gypsum required for 100 sq.ft wall (thk of plaster is 12 mm)

1 Answers   Indu Projects, Tata Tiscon,


what is the detention period for oxidation ponds

2 Answers  


When column of building is abutting the boundary line,then suitable footing advised is

0 Answers  


yasser arfatcompleted his degree in civil from which university

0 Answers  


Which types of Water Proofing to Be used in Swimming Pool.

2 Answers   CCEL, Ideal Construction‎,


What is the largest concrete dam in the world?

0 Answers  


please know me that required quantity of cement , sand , water and bricks for 1 cub meter of brick work

1 Answers   Nirman Consultants,


How steel required for 823 sqm of flooring work in 150mm c/c in single jali?

1 Answers  


What is dead load impact load live load

0 Answers   Osmani Constructions,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)