How to calculate the quantity of brick or mortar in m3.
like in 1m3 brick =....no.
.......mortar=....m3
Answer / sudar
The size of the modular brick is 190 X 90 X 90
Mortar Thickness is 10mm
Assume required brickwork volume is 1 cubic metre (m3)
Volume of bricks with mortar
Volume of 1 brick with mortar = 200 X 100 X 100 ( 10 mm mortar thickness on all sides)
= 0.2 X 0.1 X 0.1
Volume of brick with mortar = 0.002 Cum (m3)
Therefore, Number of bricks required for 1 cubic metre = 1/0.002 = 500 No.s
Volume of bricks without mortar
Volume of 1 brick without mortar = 190 X 90 X 90
= 0.19 X 0.09 X 0.09
Volume of 1 brick without mortar = 0.001539 Cum (m3)
Volume of 500 bricks without mortar = 500 X 0.001539 Cum
Volume of bricks without mortar for 1 cum = 0.7695 Cum (m3)
Therefore,
Required amount of cement mortar = 1 Cum – Volume of bricks without mortar
= 1 – 0.7695
Required amount of cement mortar = 0.2305 Cum (m3) (Wet Condition)
Dry volume of a mortar = 0.2305 cum X 1.33 = 0.306565 cum
We Assume the mortar ratio is 1:6 (1 part Cement & 6 Part Sand = 7 Part)
Required amount Cement quantity in brickwork = 0.306565 X 1/7 X 1440 kg
Required amount Cement quantity = 63 Kg = 1.26 bags (50 Kg bag)
Required amount of Sand = 0.306565 X 6/7 = 0.26277 Cubic metre (m3)
Therefore, For 1 cum of brickwork, we need
500 Numbers of bricks
63 kg of cement
0.263 m3 of sand.
| Is This Answer Correct ? | 0 Yes | 0 No |
how many AAC blocks of size 600*200*225 mm are required for 1 cu.m of area
What is the procedure and technnology behind jointing of prestessed block in Delhi metro rail project.
five requirements of infill panels for walls?
what is the crushing strength of good building stone
Are you a team player?
Should column area deducted from form work measurement of slab in building?
what is dead wall?
What type of tensile strength is handling by crank in beam? Thanks.
for pretensioning which will yield first and same for post tensioning?
what is the design procedure for building
How much for the BRC lapping in full yield and half yield < and which table to get it ?
how to calculate circular slab reinforcement (6m dia 0.15mmthick)
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)