The size of the modular brick is 190 X 90 X 90
Mortar Thickness is 10mm
Assume required brickwork volume is 1 cubic metre (m3)
Volume of bricks with mortar
Volume of 1 brick with mortar = 200 X 100 X 100 ( 10 mm mortar thickness on all sides)
= 0.2 X 0.1 X 0.1
Volume of brick with mortar = 0.002 Cum (m3)
Therefore, Number of bricks required for 1 cubic metre = 1/0.002 = 500 No.s
Volume of bricks without mortar
Volume of 1 brick without mortar = 190 X 90 X 90
= 0.19 X 0.09 X 0.09
Volume of 1 brick without mortar = 0.001539 Cum (m3)
Volume of 500 bricks without mortar = 500 X 0.001539 Cum
Volume of bricks without mortar for 1 cum = 0.7695 Cum (m3)
Therefore,
Required amount of cement mortar = 1 Cum – Volume of bricks without mortar
= 1 – 0.7695
Required amount of cement mortar = 0.2305 Cum (m3) (Wet Condition)
Dry volume of a mortar = 0.2305 cum X 1.33 = 0.306565 cum
We Assume the mortar ratio is 1:6 (1 part Cement & 6 Part Sand = 7 Part)
Required amount Cement quantity in brickwork = 0.306565 X 1/7 X 1440 kg
Required amount Cement quantity = 63 Kg = 1.26 bags (50 Kg bag)
Required amount of Sand = 0.306565 X 6/7 = 0.26277 Cubic metre (m3)
Therefore, For 1 cum of brickwork, we need
500 Numbers of bricks
63 kg of cement
0.263 m3 of sand.
Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
what r the precaution for high in atp tempareture,low in atp tempareture
in the construction of residential building what type of tank are used?where?why & what is its purpose?
Tell me about triple point of water.
WHAT GOAL DO YOU HAVE IN YOUR CARRIER?
how to calculate steel for slab or footings?
the water is flowing through a velocity of 1.5m/s in a pipe of length 2500m and dia 500mm. at the end of pipe a valve is provided. find rise in pressure 1. if the valve is closed in 5 seconds. 2. if the valve is closed instantaneously. take value of c = 1460m/s, pipe to be rigid and bulk modulus of water - 19.692x10' n/sqcm
How to calculate thickness of MAT slab & Reinforcement? The dimention of under ground water reservoir is 80'X14'X 12 ft
What is the wall thickness of NP-3&NP-4 hume pipe as per I.S code
What is componsation
how much quantity of 1.5" nails and 2.5" nails are required for conventional formwork shuttering?
What are the uses of groynes?
In foundation design, while we do the base pressure check, we normally check if the attained pressure value is less than the GROSS BEARING CAPACITY of the soil which is the sum of net bearing capacity of soil and the overburden pressure. Actually, the overburden pressure acts against the net bearing capacity of the soil and I feel that we are actually increasing the bearing capacity value and doing the check. I feel that this is NOT right. Please clarify on this.
3. A vane 12.5 cm long, 8.8 cm dia was pressed into a soft clay at the bottom of borehole. Torque was applied and the value at failure was 55 N-m. find the shear strength of the clay on a horizontal plane.
why +1 to be followed for calculating the no of bars in BBS. Please explain
What is the force exerted by the tacoma narrows bridge?