Answer / imtiyaj
0.42 is the water ratio and 1m3 concrete cement consumption m-30,380 kg something
so we give 380X0.42= answer is 159.6 ltr
| Is This Answer Correct ? | 1 Yes | 0 No |
what is smart building materials?
An invisible line should intersect a visible line with
1 Answers PSC, PSCI, SPC Systems,
as per is code, what is the minimum content of opc and ppc cement for rcc structure
How to calculate steel quantity in beam and column?
In BBS,Find out the cutting length for a 2000*2200 column with 50 mm cover?
14. List 3 of your strongest points as a worker?
What is the number of IS code of practice to be followed for hydraulic design of sewerage pipe line?
If a slab concrete is placed with M-20 grade concrete, actually it has to be placed with M-30. what are the rectifications / measures to be taken after concreting is done.
what is the productivity in aluminium shuttering per day
you are planning to paint a newly fabricated workshop building made of structural steel of 10 tons total mass.you are require to paint 1 cot of primer and 2 coats of top coat.How many liters of primer and top coat you will request
how to calculate the quantity of plaster.
How many cncrete grades are used for construction,explain with proportion,grades and where it used
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)