its depend on usaes if RMC by pump 1% ,
if manualy then min 5%
Is This Answer Correct ? | 10 Yes | 2 No |
Answer / mohd sameer khan
3 percente of wastage is allowed in concrete.
Is This Answer Correct ? | 4 Yes | 2 No |
Answer / sandy
this may depend on method by which u r doing conc.
1) Drop & Pick = manually
2) Chut method
3) conc. pump
Is This Answer Correct ? | 2 Yes | 6 No |
best option for job in construction govt or pvt for engg
what is mean by bulking of sand?
11 Answers CCCL, Kanakia Group,
can we make bricks using m10 grade cement concrete and what would be the ratio of raw materials used and price per brick ?
Before casting a basement roof slab which is connected with retaining wall surcharge load (i.e. sand or earth filling) outside the retaining wall is prohibited because of––
01m3 cement mortar in cement qty in kg
How to calculate cement qty of M10, m20, m25 ? I got the formula but I lost it.
what is the tool used at construction site for measuring cement, sand and blue metal in india.
How to convert aggregate and sand from kgs to ltrs ?
difference between fc and fc'?
0 Answers Wah Engineering College,
What is meant by Anchorage length? Development Length?
what is the meaning of sleeves in reinforced concrete????. where its coming???.