Why we stop the concrete in 1/3 rd of span length
Answer / anuranjan kumar
after l/3 tesion zone develope in mid span so always stop concreting with in l/3
| Is This Answer Correct ? | 13 Yes | 2 No |
What are the different grades of concrete & their ratios?
What is the significance of cost estimate knowledge for an architect?
what is the difference in density of fresh concrete and hardened concrete?
1 Answers GPSC Gujarat Public Service Commission,
What is the capacity of Maharashtra in power generation by winds?
5 Answers MPSC, State Bank Of India SBI,
difination of civil engineer
Why should you show Client/Engineer activities clearly on the project plan?
how to design and calculate materail quantity for concrete speedbreaker ?
how to create our resume?
0 Answers Sunraj Construction,
how to carry out rate analysis for RCC work in column using M20 ?
1 Answers Mazna Building Contracting,
Explain the importance of moment of inertia?
What is need for setting limits?
How to calculate Cement, Sand and Kapachi required for M20, M25
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)