Sir what reason the deshuttring of column 1 day after casting and slab deshuttring time 14 days after casting 



Sir what reason the deshuttring of column 1 day after casting and slab deshuttring time 14 days afte..

Answer / rethina kumar

generally concrete is strong in compression, weak in tension, that is reason we providing reinforcement in tension zone.

1.column is compression zone, so one day is enough to deshutter
2.slab is tension zone, so it need minimum 14 days to deshutter

Is This Answer Correct ?    30 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

The point of contraflexure occurs in

10 Answers  


what is called super elevation of the road?

1 Answers   PBL,


please help me to find a mix design ratio for M40....

2 Answers  


what is the basic idea of well sinking????

1 Answers   Quality Water Management Systems, Simplex, Sobha Developers,


I used Etabs software to analyse a high-rise building. And I want to use templated UBC-codes inside to calculate the Seismic load. My question is: whether or not I have to control the seismic load by base shear load which is manual calculation? (just for more clarification: I can control this by input the scale factor into Eartquake definition in Etabs) I would highly appreciate your answer.

0 Answers  






how much to get of BRC lapping in full yield and half yield ?

0 Answers   Engtex,


How to calculate 1 brss for RCC work  

0 Answers   Allied Group, Jyoti Structures Ltd,


I would like to get the formula How can i calculate the productivity of a mason in terms of brick laying and plaster. i have 6000 Sqmt of interlock laying work i want to calculate - how many masons required to do the job - in how many days can it be done - what will be the production rate in 8 hours shift/ per mason if i can get some excell sheet , it will really help me in my calculations

0 Answers  


density of flyash

4 Answers  


How many times one TMT bars bents & straight upto not broken the bar.

5 Answers   HCC,


4. Differentiate between NC and OC soils. Draw curves for (i) Stress vs Strain (ii) Volume charge vs Strain (iii) Pore pressure vs Strain for these soils

0 Answers  


what is conventional shuttering rate per square feet of built up area? what is Mivan shuttering rate per square feet of built up area? what is coupler shuttering rate per square feet of built up area?

0 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4452)
  • Electrical Engineering Interview Questions Electrical Engineering (16638)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)