The point of contraflexure occurs in
Answers were Sorted based on User's Feedback
Answer / guest
1.simply suported beam only
2.cantilever beam only
3.countious beam only
| Is This Answer Correct ? | 68 Yes | 28 No |
Answer / sanjay semwal
where bending moment is
zero and shear force is
maximum
| Is This Answer Correct ? | 18 Yes | 2 No |
Answer / shashi kumar
where shear force and bending moment zero
| Is This Answer Correct ? | 18 Yes | 10 No |
Answer / sjtbehera
Yes, the point where shear force is maximum and bending moment is zero.
It is very important to calculate shear reinforcment.
| Is This Answer Correct ? | 6 Yes | 0 No |
Answer / muraliyadav
where the bending moment just becomes zero that point can
called as point of contraflexure
| Is This Answer Correct ? | 6 Yes | 2 No |
Answer / adeel ahmed
It is a point during the analysis of structural components in which bending moment change its sign mean the point of zero bending moment and this occurs mostly in overhanging case.
| Is This Answer Correct ? | 4 Yes | 0 No |
Answer / meet
Occurs in overhanging beams only at point where bendig moment is either zero or changes sign and the shear force at that point is maximum
| Is This Answer Correct ? | 3 Yes | 0 No |
Answer / suresh bariya
a Point where shear force and bending moment both are zero.
| Is This Answer Correct ? | 1 Yes | 7 No |
What is a tensile strength? What is the tensile strength of wood?
what is stress?
What is construction mitigation management?
What is a BBS?Find out the cutting length for a 600*600 foundation with 50 mm cover
what is the percentage of silt in black cotton soil.?
I Have concrete mix with 440kg opc and having 37 mpa strengh in 7days while in 28 days only 42mpa can anybody tell me the reason for the same.
why does the most of civil engg is not intersted to going for teaching field?
sir, how to calculate steel per 1 m2
What is the Tor steel Consumption for residential building G+24 footing (thum rule) ?
i Have Completed a Intermediate Vocational (Construction technology) with Bridge course ,iam elegible to join in Institute of Surveyors(india).
Sir your company in receiver ment of civil engineering.
how much time will take for G+22 building for completion? activity wise like excavation,sub structure,superstructure,finishing,handover?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)