Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


HOW MANY CEMENT BAGS ARE REQUIRED IN 1 CUBIC METER

Answers were Sorted based on User's Feedback



HOW MANY CEMENT BAGS ARE REQUIRED IN 1 CUBIC METER..

Answer / k.k.raj

1 m^3 of cc with ratio 1:2:4 - 4.11 bags

Is This Answer Correct ?    0 Yes 3 No

Post New Answer

More Civil Engineering Interview Questions

how to calculate cut length of for a triangular portion for steel ?

0 Answers   Shashi,


If we know the N - Value of soil and required bearing capacity how do we know what diameter and length of pile to be casted? How can we check whether the dia. and lenght of pile we have selected are most economical onse?

3 Answers  


how to calculate the quantity of material in 1 cubic meter Concrete?

1 Answers   Sobha Developers,


one steel fixers how much ton steel fabrication he will do same how much tone he will binding?

0 Answers   PN, Simplex,


During reclamation how can the occurrence of mud waves can be rectified?

0 Answers  


I'm constructing my house, now at lintel level. I need belt concrete with laft..length - 22ft, berth- 11ft, one side laft for 2ft, *22ft length. Kindly inform me centring cost only, without material cost.

0 Answers  


For 12mm thick and cement plastering 1:6 on 100sqm new Brick work the quantity of cement required is

1 Answers  


how many bricks required for below volume 1. depth filling 0.00 Qty 1.61 & Unit Cu.M 2. D-Filling 300 Qty 2.0 & Unit Cu.M 3. D.Filling 450 Qty 2.24 & Unit CU.M 4. D-Filling 600 Qty 2.44 & Unit Cu.M

1 Answers  


who to calculate the bar bending schedule?

3 Answers   APPSC,


What is specific gravity???

0 Answers  


Why silt content not allowed more than 6% for Sand ?

2 Answers   CCEL, L&T, NTPC,


density of crush sand & crush stone or grit powder

0 Answers   Godrej, L&T,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)