Any body please let me know how to prepare Method Statement
for Bored Cast in situ piles.

Answers were Sorted based on User's Feedback



Any body please let me know how to prepare Method Statement for Bored Cast in situ piles...

Answer / sjtbehera

See in piles some statment are record in field book some
are as follows
1. what is dia of pile
2. what is length of penetraion of pile in one hour.
3. what is the finial depth of termination of pile.
4. what is the cum casting of pile.
5. plate laoad test of pile.

Is This Answer Correct ?    3 Yes 2 No

Any body please let me know how to prepare Method Statement for Bored Cast in situ piles...

Answer / prashanth

1. what is dia of pile
2. what is length of penetraion of pile in one hour.
3. what is the final depth of termination of pile.
4. what is the cum casting of pile.
5. plate laoad test of pile.
6. Dia of steel to be used.
7. Grade of the concrete as per design and Pouring of the
concrete in layer by layer.
8. Testing of pile like Intergrity test.
9. Removal of the termination slurry concrete.

Is This Answer Correct ?    1 Yes 0 No

Any body please let me know how to prepare Method Statement for Bored Cast in situ piles...

Answer / siaf rizvi

Above all,
1# Sample of rock @ termination level.
and mant more which u can learn as per exprience.

Is This Answer Correct ?    0 Yes 0 No

Any body please let me know how to prepare Method Statement for Bored Cast in situ piles...

Answer / shubham rana

It is suggested that all utilities such as (cables, pipelines ,gaslines , sewerlines) falling within excavation area are diverted away in advance to avoid damage to such utilities during the excavation/ construction phase.

Initial hard strata of the ground is cut by a “Drilling Bucket” , which is a box like structure attached to Rig machine and has a sharp toothed like structure below it .

Then a temporary Mild Steel casing for about 4 to 6 m (approx) length from the ground level will be driven to protect loose soil from falling in the bore hole.

Then a Polymer Powder is added to form a slurry which provides a clear, solid-free, viscous borehole stabilizing fluid till the excavation is done for the piles. Polymer Slurry has a pH of 11 to 12, Specific Gravity of 1-1.04 and Viscosity 65 to 140.

After drilling borehole, reinforcement cage is lowered. While lowering the cage care has to be taken to install it in gap of 10 m and fillet weld of 6mm is to be provided to join upper end of previous cage with lower end of cage to be lowered.
After cage lowering , Tremie Pipe generally of diameter 200mm and 2-3 m length are lowered one by one and tied to each other . The gap between the bottom of the bore to the end of tremie pipe will be min 300mm.

Upper end of the tremie pipe is connecter to funnel shaped “Hopper” , to which concrete mix is poured .

As the Concreting Proceeds Concrete mix being denser replaces the Polymer slurry and slurry comes out of the borehole and is diverted away from the hole.

A very high Slump Concrete 150 – 200 mm is needed for piling ,regular compaction to be provided by Hydraulic Drilling Machine so as to ensure proper lowering of concrete .


After Few days of setting sonic tubes are filled with water and then in one tube ultrasonic wave emitter probe and in other receiver probes are inserted, knowing the distance between the two tubes , Relative energy, waveform and differential time are recorded and mapped. This is called “Cross Hole Sonic Logging”.

This gives qualitative idea of the structural soundness of the concrete throughout the pile and hence structural integrity of pile can be verified by this method.

Is This Answer Correct ?    0 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

What is the difference between stress and strength?

16 Answers  


how much quantity of cement and sand required for construction of 10 cum brick work( Brick size 3"*4"*9"(Standard size ) an d for 10 cum construction of SSM (Size stone masonary) with Cm 1:6 for both.

11 Answers   GRC, KEC, L&T, Techno Electric and Engineering, UPENN,


what is the minium content of cementous material per cu meter

2 Answers  


Adout concrete

1 Answers   Bhel, TATA,


how to calculate for ramp slop?

3 Answers  






what is fineness modulas of sand ?

4 Answers  


In a beam,stirrups are placed closely at ends than at centre due to shear.similarly where would ties be closer to each other-at center or at ends in a column and slab.

0 Answers  


what is thumb rule exactly?

2 Answers  


Slow setting admixture is used in mass concrete because of – –

4 Answers   Reliance,


how can change 10mm dia @130c/c bar spacing to 8mm dia

5 Answers   TATA,


Whats be the minimum foundation depth of multistoried building as per height of building in individual footing?

0 Answers  


What are some structures that may be subjected to fatigue?

0 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)