Answer / carl_ellis
Many manufacturers make all positioners a double acting
positioner and install a plug in the 2nd port and call the
model with the plugged 2nd port a single acting positioner.
No guarantee that all manufacturers do so, but it's true for
some of them.
You have a double action positioner - install a plug in the
2nd output port, plumb it to air and an actuator, give it
try as a single acting positioner and see if it works.
What do you have to lose?
Carl Ellis
Measure First
| Is This Answer Correct ? | 3 Yes | 0 No |
why 4 to 20 ma used at 0 set
plz you help about Que paper of mahagenco previous your,any model paper relad to it{maharastra power genration}
Good Evening all.My question is - For a feed water line to an equipment if i need to measure the flow we will use orifice /magnetic/vortex depend on cost/spec.If i need to measure a ''Alarm''signal and ''Interlock'' from one point i think we can use orifice type in one location with 2 different tapping points - one for alarm and one for an interlock to flow valve..If in case i need to have both these signals(Alarm & interlock) from magnetic flow meter,is it possible??will 2 seperate sensors will be located inbuilt r we can program it ??..i thk we can have one transmitter with these 2 signals...need to know any technical issues are there?pls clarify
What is the difference between a PLC (Programmable logic controller) and DCS (distributed control system)?
Introduce yourself which is not present in your biodata?
What are three main programming in PLC
Coal mill Instruments Equipments for cement plant And process diagram ?
what is flow equation of kg/hr to m3/hr
why pneumatic control signal output is use 0.2 to 1 kg/cm2
hello i'am samad.Any one Can help me! How to calibrate Vaccum Transmitter DP Type range 0 - 50 mbar abs by hand pump calibrator.
i have done DAE in Instrumentation and Process Control. i have applied for an apprentice training in chemical company after three day my interview will be conduct but i need more information about industrial process control and controller. my e mail is imran_dilsetu@yahoo.com please tell me interview question relative to instrumentation ?
what is your eligibility criteria for freashers?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)