how to calculate rate analysis for column shuttering
Answers were Sorted based on User's Feedback
Answer / rustam jamal
Assume Column Size- 1.200x0.300 and Height = 3.000
than Qty for Conc. = =1.2x0.30x3.0= 1.080Cum
Shuttering Area = 2x1.2x3.0=7.20
= 2x0.30x3.0=1.8
Total =9.0Sqm
In 9.0sqm Shutterin 1.08 Cum Conc. req.
so For 1 Cum Shuttering Qty = 8.333
In case of Columns we required 8.33 sqm of shuttering area
in 1 Cum of Concrete
Is This Answer Correct ? | 88 Yes | 31 No |
Answer / ajinkya patil
for 1.2x0.3 c/s and 3 m height
total shuttering area = ((1.2*2)+(0.3*2))*3= 9 sq.m
calculate total plywood or shutters required
a)cost of ply or shutter panels.
b)cost of supporting material required.
c)labour cost of shuttering.
d)labour cost of deshuttering.
e)jointing materials like nails & tie bars & other miscellaneous material
cost per sq.m= (a+b+c+d+e)/total shuttering area
Is This Answer Correct ? | 26 Yes | 7 No |
1) why bent up are provided at l/4 or l/5 distance not at l/8or l/10? 2) why extras are provided in beams at top and why upto 0.3l distance max.? 3) why chairs are provided in two way slab?
How many weight per 1meter cube of concrete for column.
In few lines, please be elaborative on extras and talents that make you a potential candidate for the post:
Dear sir, What is the procedure for total station?How to calculate?
16. What do you consider to be your greatest achievement so far and why?
what is tie-beam?where it used?
12 Answers HCC, Titan America,
how many square meter plastering get from 1 cubic meter cement mortar for a thickness of 12mm
the minimum percentage of steel for 2m rcc slab
what is westage % for steel, concrete,tiles,pains as per indian staderd code?
6 Answers DLF, Engineering, Lodha, Tata Steel Limited,
what is the technical word for column and beam joint
what is mcArther pile?
1 Answers Kerala Public Service Commission,
WHY THE WIDITH OF COLUMN IS TAKEN FOR DESIGN OF ISOLATED FOOTING??