Answer / prashanth
only slump test at hte time of pouring the concrete.
Is This Answer Correct ? | 9 Yes | 0 No |
Answer / rajnath rajbhar
Slump test
Sample collection (Cube)
Temp.
Is This Answer Correct ? | 3 Yes | 0 No |
Answer / utsav patel
slump test
and 2nd factor is temprature of concrete as well as temp of atmashphere...
Is This Answer Correct ? | 1 Yes | 0 No |
Answer / sjtbehera
Yes, slimp test, compaction test, cube test is after,
Is This Answer Correct ? | 0 Yes | 0 No |
In a given rcc design, how to calculate quantity of steel, for all practical purpose of construction?
Explain the latest method to detect a crack in a building?
how much the ratio of the m15, m25 .......etc
What is the density of most of construction materials?
# 1. Size of slit content in sand. # 2. Gravity of sand # 3. Water observation capacity of sand. # 4. minimum crushing Strength of sand.
cement mortar1:5 12mm thick and one bags cement how much area pleastering please give anwser
12 Answers DeSigns Inc, L&T, Marg, Sand, Vee Technologies,
what is the minium content of cementous material per cu meter
for solid cement brick without fly ash,we use dust,6mm,12 mm jelly,water my question is what Proportion we mix dust,6mm,12 mm jelly,water ? for good strength brick.
Elaborate advantages & disadvantages of using crusher dust instead of sand in rcc work.
How many cement bags of 50Kgs will be required for 2600sqft terrace with thickness of 5".
What is Heavy Concrete & Normal Concrete
What is the procedure to calculate the compaction of sand?