what is intrument termination
what is commisioning
Answers were Sorted based on User's Feedback
Answer / james c
When installing instrumentation, cable is run from the marshelling cabinet, or some control system to the instrument in the field. The act of attaching the cables to the actual electrical terminals of the instrument or input output terminal at the Transmitting or receiving end is called Terminating the instrument. I.E instrument termination. Usually the instrument loop is installed in stages, where the instrument is physically mounted in the field, cable is pulled and run in cable trays or buried in trenches, and the ends of the cables are terminated.
Once prior to completely terminating a loop, the cable run is normally loop tested. I.e. Point to Point continuity checked. Once the cable is found to be good, and the instrument terminated, calibrated and tested to be functioning at the control system, the instrument is said to be commissioned. I.e ready for service. That is called commissioning. Usually commissioning forms a entire stage/phase of its own in a project.
| Is This Answer Correct ? | 8 Yes | 1 No |
Answer / vasavi power services pvt ltd
Commissioning means to run machine with desired output by
satisfying some conditions provided by manufacturer
| Is This Answer Correct ? | 1 Yes | 1 No |
Answer / jatin
commissioning of instrument has to deal with many steps. Availability of Cable tray and trenches. Laying of cable from Instrument to Junction Boxes and then Junction Boses to Marshalling Cabinet, which are connected with DCS/PCS controller. After laying of cables termination has to be done. which can be checked with the continuity of cable. the commissioning of instrument is still pending. The loop checking has to be performed for successful commissioning.
| Is This Answer Correct ? | 1 Yes | 2 No |
why r using 250 resistances
what is gas metering system? gas chromatograph? and gas compressors?
How a oxygen sensor & analyzer work at boiler or furnace, what’s the principle & science is beyond this, How O2 sensor scene & convert signal & move toward analyzer & analyzer show reading in percent?
1 Answers GS Engineering Construction, KNIC,
1.can you use SCADA instead of DCS,DCS instead SCADA 2.Difference between DCS and PLC,can their role be reversed i.e. role interchange 3.Difference between RTU and PLC
0 Answers IOCL, Lakshmi Machine Works,
how 3 out of 2 Logic/interlocks works? give brief explanation with help of diagram.
Basically iam Instruemntation Engineer, but Iam interested in Instruments design engineering, so plz guide, is there any course, training or Softwres to become Instrument design engineer??.
0 Answers Honeywell, Tata Steel Limited,
How many input(Analog and digital) and outputs(Analog and digital) are there in DELTA v DCS Version 7.0?
Explain level troll principle & interface level measurement.
Tell me the field calibration procedure step by step with diagram of pressure gauge, pressure switch, pressure transmitter, temperature switch, level switch, flow switch, flow transmitter.
ALL INSTRUMENTS WORKING PRINCIPLE.
3 Answers Blanco, India Cements, TVS,
what is function test.
we are having yokogawa centum cs3000 dcs in our power plant. i need some of the operator guides NOT to appear in HIS0163 AND HIS 0162 but it shoul appear in HIS0164 HOW TO DO IT?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)