bar bending schedule?

Answers were Sorted based on User's Feedback



bar bending schedule?..

Answer / nitin

bar bending schedule is nothing but the required steel which is calculated in a format like sr.no,description of item,shape,size,no of item,no of bars,cutting length,unit wt.,total wt.

Is This Answer Correct ?    21 Yes 5 No

bar bending schedule?..

Answer / muthuraj

It's a short form of BBS to used Steel cutting bending of
reinforcement work IS 2502 & SP34.

Is This Answer Correct ?    9 Yes 4 No

bar bending schedule?..

Answer / pratham rajoriya

BBS mease actual length of TMT bar after all bend deduction and addition of side curtail bar which used in site for any member like beam,column,slab etc.

Is This Answer Correct ?    0 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

Why do we use badarpur or crusher sand with coarse aggregate in a concrete mix?

1 Answers  


how to calculate the runner (2*3) qty in cft. the length is 8 feet.

6 Answers   CCCL, Gammon, Greenko, L&T,


Required amount of Steel bars, cement/ square feet for roofing of residential building upto 3rd floor.

0 Answers   Sail,


Till how many days can we keep a cement bag without using? And on what conditions the cement will get spoiled?

4 Answers  


How much quantity of cement and sand required for the inlining of 610mm dia MS pipe 8.7mm thk.Inlining thickness is 10mm and CM ratio is 1:1.5.

0 Answers   IVRCL,






what is the meaning of degreasing of the euipment or line.

1 Answers  


What is differnce between founadation & footin ?

5 Answers  


which oil is used for mivan shuttering?

3 Answers  


what is stress?

4 Answers   CCCL,


1. 1. The mass of a chunk of moist soil is 34 Kg and its volume is 0.012 cu. Meter. After drying in an oven, the mass reduces to 14.25 Kg. Determine the water content, the density of moist soil, the dry density, void ratio, porosity and degree of saturation. Take G = 3.25

0 Answers  


what is mean by hysd bar?

8 Answers   L&T,


Pls. help. If a contract was awarded to a contractor in april 2012 with steel & cement base price as rs. 45/kg & 250/bag. Now in oct. 12 steel cement price becomes 55/kg & 290/ bag. How escalation will be calculated? Pls. tell complete calculation Regards,

4 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)