bar bending schedule?

Answer Posted / nitin

bar bending schedule is nothing but the required steel which is calculated in a format like sr.no,description of item,shape,size,no of item,no of bars,cutting length,unit wt.,total wt.

Is This Answer Correct ?    21 Yes 5 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

How many Rod required for 58 feet by 24 feet roof slab which is supported by 5 * 3 = 15 Column. Six Stored building Roof Slab = ? Ton 15 Column = ? Ton Slab Beam = ? Ton

1702


how to find out hard strata in bored pile when the DMC method adopted.

5336


What is the quantity of metal 1 & metal 2 to be used in 100 cft concrete?

2607


i need gate exam civil engineering question papers with answers

1752


(Project Management Topic) What are the important criteria in the successful realization of the project?

1668






How to calculate the area of a irregular sized land in square feet?and what will be the total area of this land South-51.1ft , North-47.7ft , East-53.3ft , West-54ft ?please explain me how to calculate?

1497


what is diversion?

1753


whats is difference between anchorage length and development length

1379


Kindly post me previous year interview questions with answer for post of Manager (civil engg.) for NTPC, IOC , GAIL etc. I have interview on july 2013.I will be very grateful to you. Please guide me.

1796


Can we use the flyash bricks in brick bat coba?

1078


how many litres of enamel paint required for 5000 sft of site?? 

1489


what is BPM in concrete demolition hammers. what is better a higher value or lower

2242


While calculating the weight of the steel per running meter, the formula used is [(dxd)/162]. Why 162 is used in denominator & how it is derived?

1140


very simple or less time consuming formula for reinforcement calculation by moment

1055


what is kribs is supporting?

1602