concrete mix design for M 30 Grade
M30 ( 1 : 2 : 2.87)
Cement : 380 Kg/ M3
20 mm Jelly : 654 Kg/ M3
12.5 mm Jelly : 436 Kg/ M3
River sand : 760 Kg/ M3
Total water : 187 Kg/ M3
Admixture : 0.7%
Fresh concrete density: 2420 Kg/ M3
Note: Sand = 760 Kg with 2% moisture (170.80+15.20)
| Is This Answer Correct ? | 2 Yes | 2 No |
1 cum of 60*25*25 block cost 187 dirhams. Find the cost of 1 sqm of block ?
how to calculate 1:5:8 ratio concrete cement, sand, metal and water please give me brief calculation
why the compressive strength of concrete is calculated only after 28 days.why not after 25, 26,27 days..
CAN V USE CRUSH SAND FOR CLAY BRICK MASONARY
sir please send me campus placement questions in civil engineering
What is thumb rule for deep trench excavation
What is zoning permit?
What are the functions of grout inside tendon ducts?
What is the ratio of cement, sand, aggregate of mix M25
20 Answers CCCL, Sarvottam Cement,
how to calculate the number of cement bags required for 1m3 of work
Can we weld hot rolled steel ASTM A615 ?
how many cement bags rquired for solid block construction for 100 sqft in 1:6 proportion?
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)