why the compressive strength of concrete is calculated only after 28 days.why not after 25, 26,27 days..
Answers were Sorted based on User's Feedback
Answer / joseph
The compressive strength is calculated at 3 ,7 ,28 days.if
you want to transport a precast structure of the grade
40/20 ,it should aquire 60% of design strength ..here it is
60% of 40.In seven days we shoul attain 75% of design
strength. Then your answer ; all the test cubes must attain
their 100% of design strength in 28 days. to ensure this
one we are taking test in 28 days .if cubes fail we have to
go for field test such as smith and hammer test or pulse
velosity (BS 12504 ).
Refer BS 1881 part 116
there are some factors to asses the test result
refer BS 6089
| Is This Answer Correct ? | 15 Yes | 5 No |
Answer / sagar sontakke
As soon as we add water to the dry content of the concrete, process of heat of hydration starts and this process will require a very long time to complete.Almost 90% to 95% of this process is completed within 28 days and remaining takes a year or two.This means that concrete attains 90% of the strength at 28 days. So to judge whether concrete has attained the desired strength, we have to test the concrete at 28 days.
| Is This Answer Correct ? | 12 Yes | 2 No |
Answer / imran
Answer # 4 is the correct answer of this question.
| Is This Answer Correct ? | 1 Yes | 0 No |
Answer / kanchan
Its is because the maximum strength i.e. 99% of strength gained by a cube in 28 days
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / utsav patel
strength is depend on hydration process. after 28 days aronnd 68% strength is gained by concrete. hydration process is not confined up to certain period is longlasting process .
| Is This Answer Correct ? | 0 Yes | 5 No |
Answer / suresh.s
the cement strength also prepared for 28 days
| Is This Answer Correct ? | 2 Yes | 10 No |
Answer / silpa
Cube Size=150 mmX 150 MM
Area = 22.5 Sqm.
Stress = Load / Area E
Eg : 600/22.5=26.26 N/mm
| Is This Answer Correct ? | 2 Yes | 10 No |
In a beam tension is always at the bottom but sometimes when we design using staad we get more number of rebars at the top compression zone Why?
How to arrive d*d/162 , for finding the kg per meter , wt of steel
How to calculate woden area in sft and Cft
What are the different softwares used for cad?
How to calculate cement required for m20,m5 grade
what if i want to lap a 20mm dia and a 16mm dia together wat will be the lap length?? a) 1m b) 80mm
How its coming concrete grade M 20 means 1:2:4. how it coming 1:2:4.
Explain Different types of raft foundation
do you think we shall remove un wanted soil for foundation excavation even if the thickness of the soil strata is more than 8m ?
Name the main components of a cad gui?
TO RESISIT TORSION IN BEAMS WHAT KIND REINFORCEMENT IS PROVIDED?
WHAT GOAL DO YOU HAVE IN YOUR CARRIER?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)