Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


why the compressive strength of concrete is calculated only after 28 days.why not after 25, 26,27 days..

Answers were Sorted based on User's Feedback



why the compressive strength of concrete is calculated only after 28 days.why not after 25, 26,27 da..

Answer / joseph

The compressive strength is calculated at 3 ,7 ,28 days.if
you want to transport a precast structure of the grade
40/20 ,it should aquire 60% of design strength ..here it is
60% of 40.In seven days we shoul attain 75% of design
strength. Then your answer ; all the test cubes must attain
their 100% of design strength in 28 days. to ensure this
one we are taking test in 28 days .if cubes fail we have to
go for field test such as smith and hammer test or pulse
velosity (BS 12504 ).

Refer BS 1881 part 116
there are some factors to asses the test result

refer BS 6089

Is This Answer Correct ?    15 Yes 5 No

why the compressive strength of concrete is calculated only after 28 days.why not after 25, 26,27 da..

Answer / sagar sontakke

As soon as we add water to the dry content of the concrete, process of heat of hydration starts and this process will require a very long time to complete.Almost 90% to 95% of this process is completed within 28 days and remaining takes a year or two.This means that concrete attains 90% of the strength at 28 days. So to judge whether concrete has attained the desired strength, we have to test the concrete at 28 days.

Is This Answer Correct ?    12 Yes 2 No

why the compressive strength of concrete is calculated only after 28 days.why not after 25, 26,27 da..

Answer / imran

Answer # 4 is the correct answer of this question.

Is This Answer Correct ?    1 Yes 0 No

why the compressive strength of concrete is calculated only after 28 days.why not after 25, 26,27 da..

Answer / kanchan

Its is because the maximum strength i.e. 99% of strength gained by a cube in 28 days

Is This Answer Correct ?    0 Yes 0 No

why the compressive strength of concrete is calculated only after 28 days.why not after 25, 26,27 da..

Answer / utsav patel

strength is depend on hydration process. after 28 days aronnd 68% strength is gained by concrete. hydration process is not confined up to certain period is longlasting process .

Is This Answer Correct ?    0 Yes 5 No

why the compressive strength of concrete is calculated only after 28 days.why not after 25, 26,27 da..

Answer / suresh.s

the cement strength also prepared for 28 days

Is This Answer Correct ?    2 Yes 10 No

why the compressive strength of concrete is calculated only after 28 days.why not after 25, 26,27 da..

Answer / silpa

Cube Size=150 mmX 150 MM
Area = 22.5 Sqm.
Stress = Load / Area E
Eg : 600/22.5=26.26 N/mm

Is This Answer Correct ?    2 Yes 10 No

Post New Answer

More Civil Engineering Interview Questions

how to take quantity of steel per cum in columns

2 Answers   ERRA, Skyline Builders,


Is it worthwhile to carry out tests on particle density of soil particles for geotechnical design?

0 Answers  


why primer application is required before applying putty

3 Answers   Ramky,


What is ngl level and how it is transfer to column or beam??

1 Answers   Hitech,


How do piles bear loads

3 Answers  


Deshuttering time for slab 6.15 meter

2 Answers  


why do we not deduct volume of steel to find actual volume of concrete in practical???

0 Answers   Lodha,


Middle point of any slab is raised 10-12 mm during shuttering work because––

4 Answers  


How much cement+aggregate+sand will be required for making K 150 ready mix for 1 CBM. Strength of Concrete is not mentioned only detail is K150, what i understand of K150 is the weight of cement and what does kg/m3 means.What will be the design for K300 concrete.

2 Answers  


if any chance to getting a set of solved major building estimate with the drawing.(soft copy)

0 Answers  


WHAT IS THE % OF CONCRETE WASTAGES PERMITED IN A LARGE PROJECT ? AND WHICH IS CODE TO BE REFERED.

0 Answers   L&T,


How to calculate the volume of sloped isolated footing?

1 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)