Answer / joseph
The compressive strength is calculated at 3 ,7 ,28 days.if
you want to transport a precast structure of the grade
40/20 ,it should aquire 60% of design strength ..here it is
60% of 40.In seven days we shoul attain 75% of design
strength. Then your answer ; all the test cubes must attain
their 100% of design strength in 28 days. to ensure this
one we are taking test in 28 days .if cubes fail we have to
go for field test such as smith and hammer test or pulse
velosity (BS 12504 ).
Refer BS 1881 part 116
there are some factors to asses the test result
refer BS 6089
Is This Answer Correct ? | 15 Yes | 5 No |
Answer / sagar sontakke
As soon as we add water to the dry content of the concrete, process of heat of hydration starts and this process will require a very long time to complete.Almost 90% to 95% of this process is completed within 28 days and remaining takes a year or two.This means that concrete attains 90% of the strength at 28 days. So to judge whether concrete has attained the desired strength, we have to test the concrete at 28 days.
Is This Answer Correct ? | 12 Yes | 2 No |
Answer / imran
Answer # 4 is the correct answer of this question.
Is This Answer Correct ? | 1 Yes | 0 No |
Answer / kanchan
Its is because the maximum strength i.e. 99% of strength gained by a cube in 28 days
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / utsav patel
strength is depend on hydration process. after 28 days aronnd 68% strength is gained by concrete. hydration process is not confined up to certain period is longlasting process .
Is This Answer Correct ? | 0 Yes | 5 No |
Answer / suresh.s
the cement strength also prepared for 28 days
Is This Answer Correct ? | 2 Yes | 10 No |
Answer / silpa
Cube Size=150 mmX 150 MM
Area = 22.5 Sqm.
Stress = Load / Area E
Eg : 600/22.5=26.26 N/mm
Is This Answer Correct ? | 2 Yes | 10 No |
Which is code is used for measurmenr of reinforcement steel work.
which is the cheapest type of temporary flooring(say for using 6 months on)?
what is design life of steel structures??
WHAT GOAL DO YOU HAVE IN YOUR CARRIER?
all rod lapping formula
how we check the thickness and line of ceiling plaster.
How much kg of sand,cement will be for 1 sqmt(Blockwork-size 400x200x200)1:4 ratio & same for plaster
Which type of plywood & sizes using in construction projects ?
How can we find out the clear cover for a circular ring and rectangular ring..
If at site iam supposed to get M30.But by mistake i got M20 mix. How could I differentiate the mix before placing?
what is bolt value?
Define graphics window?