Steel calculation formala for column,beam and slab.
Answer / vijay kumar.g
beams:(is 456-2000)
mini Asv =(0.85*b*d)/fy
maxi not greater than0.004bD
columns:(is 456-2000)
mini 0.8% of gross c/s area of the column
maxi not more than 6% of gross c/s area of the column but pratical purpose used 4% of gross c/s area of the column
slabs:(is:456-2000)
mini 0.15% of c/s area of the slab this value can be reduced to 0.12% when used HYSD bars
| Is This Answer Correct ? | 11 Yes | 1 No |
if the length and breath of footing is 1.2m x 1.2 m what will be the length and breath of foundation trench
What the advantages and disadvantage of using 90mm and 100mm bricks for a wall of a house? Thanks for any input.
Management diagram of your project isβββ
How du we calculate dry cement (in Bags) for any concrete, also sand and aggregate? How many bags of cement does 100 cft of concrete 1:2:4 require? Procedure to calculate the required amount. Also if there is any easy thumb rule to find out.
What are the Types Of DPC and its Thickness used?
how much binding wire is required for one tone steel
20 Answers Gammon, Hinduja, Jindal,
what interested you in becoming a civil engineer?
what cement consumction plaster 15mm think per sqmt 1:3&1:6 how much kg.
M40 grade concrete has 40 n/mm2 strength.here what"s mean by n?
how to calculate MR 9(derivation)
What is the best mixing ratio of concrete materiloas for raft foundation?
what is curing?
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)