Why in India distribution transformer are connected in Dyn11
when we know capacity of v-v connection can be increased by
adding only a single transformer?
In India according to indian standard we use + or - 30 degree phase shift between LV and HV side.
so we can use Dyn11(for star LV is leading delta HV with 30°) or Dyn01(for delta HV is leading star LV with 30°)
It depend on 12 hour clock like 1=30°,2=60°......11=330°or(-30°),12=0°
| Is This Answer Correct ? | 6 Yes | 0 No |
Dear Friends, Need your help for connecting APFC panel, Quotation : I have 2 No’s 1000 KVA Transformers, both transformers are having separate APFC panels, ( Tr-1,400KVAR, TR-2,450 KVAR) Now I want to stop One transformer, present load is 650Amps, Max, So One transformer is enough, I have switched OFF TR-1, but PF is not maintaining properly, its 0.5, So now I want to connect TR-2 APFC also in TR-1 Loads, Can any one answer for my Quotation with drawing, how to connect TR-2 APFC panel in TR-1 Loads,
why slipring motor , at full speed run as squirrel cage motor?
what is rotor earth fault protection scheme in hydro generator & what is dc field flashing ?
Why the power factor of the alternator in power plant is kept .8 lagging. Can't we maintain it at 1.
what is hourly consumption of coal in therma plant
What is a surge supressor why its is used in synchronous generators
which one is more costly:single phase induction motor or 3 phase induction motor??give proper reasons..
CAN ANYBODY EXPLAIN WHAT ACTUALLY MEAN BY THE PHASE DEFFRENCE? R,L,C CIRCUITS?
What is the difference between MCB and Earth MCB? What is the working principal of MCB?
1. which type of transformer connection is preferred in case of power supply transformers? (A) Star/Star (B) Delta/Delta (C) Star/Delta (D) Zig Zag/Star 2. In a power transformer usuall which winding is closer to the core? (A) Primary winding (B) Secondary winding (C) Low Voltage winding (D) High Voltage winding 3. The power factor of a purely inductive load is (A) Zero (B) Lagging (C) Leading (D) Unity.
9 Answers CECRI_Central_Electrical_Research_Institute,
when the supply of MSEB is cut off & all the load of the industry is driven on generator at that time the capacitor which is connected in industry for power factor control is switched off why?
what should be the resistance between two winding. Let 10 kw motor
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)