i need the how much materials are needed for cubic feet of
concrete?
Answer / guest
FOR PROPORTION 1:2:4 FOR 1CU-MT WORK OF CONCRETE CEMENT REQUIRED AS FOLLOWS
CEMENT ---6.5 BAGS
SAND ----0.434 CU-MT
KANKAR --0868 CU-MT
| Is This Answer Correct ? | 4 Yes | 0 No |
why we are doing post tensioning in beams and slabs. it is economical compare to rcc? how?
Dear Engineers, Can you please advise me the material requirement to construct a room 4 M x 4 M hight 3.75 meter 1. No. of Standard Brick 2. Requirement of Cement Bags 3. And Concrete for Steel, Cement, sand, etc Thanks
what is 3.14 indicates for cutting length of stirrups
What is the bearing capacity of black cotton soil, normal soil and rock?
what will happen if we use milk or oil in the place of water in concrete??????????
Describe the role of independent Quantity surveyor?
When you received a RA Bill of contractor at HO duly checked and certified by Site In-charge, How to know at a glance it is complete in order, do have any one checklist format in this regard.
why +1 to be followed for calculating the no of bars in BBS. Please explain
9. What have you done to improve or develop your knowledge / professional qualifications in the last year?
brick work 1cum kitne cft hote hai
what is the concrete mix design ratio of railway sleeper??????
how to do rate analysis for P.C.C 1:4:8 for 2.83cum(100cft)
2 Answers Unity Infraprojects,
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)