1.how to calculate the nails qty in shuttering of column,beam, shear wall.
2.how control the binding wire wastage in building project.
3.
Answer / ratheesh
.750grms to 1Kg nails for 1sqm shuttering.
u can use single binding wires
Is This Answer Correct ? | 2 Yes | 2 No |
what is perfect ballast for supporting the rails
How can we convert weight batch to volume batch for m30 mix
which type of cement uses for R.C.C. & why?
2 Answers Ideal Construction,
I have a slab of 20cm thickness of 20m by 4m in wich we are installing 15 tons electric panels , and we have put 4 H-shaped columns under the slab but we have done many cores in the slab which seems very normal , can you help me by telling me how to calculate the bearing capacity of the slab or give me an idea if i should increase more columns Note: load distribution area 12*1.5 m2
0 Answers First American Corporation, GS Infra, L&T, Real Sociedad,
If the design mix of M-30 grade concrete is 1:1.5:2.8 (By Weight)& W/C ratio is 0.45, then what should be the volumetric mix for the same ?
How do you calculate load bearing capacity of a waffle slab?
What is BDF flooring?
Concrete how muvh strenght gain 7days,14day,s,21day's,28day's&56day's after curing
How can calculate the number of bricks.....? Give me answer hurry uppppppppp
What is thumb rule in quality and quantity estimation of a Residential building??
0 Answers Ascent Constructions,
Define What is the distance between railway tracks?
why demand factor less then 1 ?