In my project i am layout cables under the Maintainance bay
/Maintainance yard in the TG Building. Whether in this route
i can lay the H.T.Cables??? i am taking all H.T cables from
the H.T Transformer to the TG Building..
Answer / annonymous
Usually we dont lay any type of cables in the maintenance bay, but you can lay it, but make sure it does not physically interfere with the maintenance activities i.e. equipment handing etc. or block the access ways there.
Also, your client may also not permit you to do so.
Is This Answer Correct ? | 1 Yes | 0 No |
Draw the single line diagram of the power station?
Why is making current of CB always greater than CB breaking burrent?.
How to Design green buildings services? What is the advantage to design green building?
What are the protections for HT Motors?
what is the purpose of vector group in a transformer ? if 2 tranaformers r connected in parallel the vector group is same or not? for parallel operation 2 transformers of different manufacturers maintain same vector group or not?
How to calculate & connection of 900KVA generator 2 sets & load(1500A)? How to choose cable size and ACB size for this load & generator? please explain me detail. Regards, Mr.Han
control & auxilary circuits used for circuir breakers
how can we generate electricity????
what is meant by auto transformer?
nwhat are the main Components of servo motor?
why is the vector group analysis done in transformer tests
28 Answers K K Rao, Lloyds, Nicco Engineering Services Limited, Qatar Petroleums,
Why is remote backup preferred to local backup?