Answer / wareagle
If you start all of the motors at the same time then you
will have the sum of the lock rotor amps time the number of
motors occurring at the same time. You may trip the primary
transformer breaker.
| Is This Answer Correct ? | 4 Yes | 0 No |
WHAT IS FORMULA TO KNOW TO BACKUP TIME OF POWER PLANT 48V/50AMP DELTA POWER PLANT
how can synchronous generator can be used as synchronous condenser?
What is maximum AC & DC transmission voltage in India? and where?
what is the defination of electrical engineer.
What is control system?
How many safety of Disel Generator
what is the Knee point Voltage?
what are the application of over current relay?
What is mean by nominal voltage,Explain?.How much nominal voltage?.
what is distribution board and panel board
Why capacitor is blow when I am starting motor ?
How to calculate the size of cables (all minium/copper) for a particular load
1 Answers BSL, Galaxy Power System,
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)