what is the real de-shuttering time for rcc column,slaband
wall
Answer Posted / royalcivil
the de-shuttering time for the slab is 21 days must.
for the column it should be minimum of 1 week
| Is This Answer Correct ? | 10 Yes | 26 No |
Post New Answer View All Answers
difference between trapezoidal and pedestal footing and how the load acts on that
What is the procedure of concealed plumbing in toilets?
what is idealized curve for concrere and steel
What will you do if a portion of load bearing wall collapses under your supervision?
Can we use Polystyrene as a Bitumen modifier !! if so is it a good MS research topic ? and what type of laboratory tests will be conducted during Research work ??
how many shuttering material required for 1000 sq.m built up area.
howto calculate the quantities of material used in fly ash brick after finding the volume??
Write short note on construction programme for pile foundation.
How to build the floor to ceiling bookcase?
what is the permanent solution applied for restoration of leaning tower of pisa?
what is cross hair cursor?
What are the advantages and disadvantages of lead products in construction?
if we know load bearing capacity of the soil and building load falling in each footing, then how to choose the type of foundation??? and if it is shallow foundation then which type of shallow foundation should be choosen i.e either strip or isolated or raft or combined or cantilever footing???????
Dear Sir, I work in hydro project. I want to hire Scorpio/ Bolero on monthly basis. But how can i justified its amount (Hourly basic). Please solve my problem
it is a corrected question." make a list of engineering property(properties) of soil.