suppose we have a tendency to make a hole on the surface of
the beam, than where we goes to make it?
Answers were Sorted based on User's Feedback
Answer / karthickrock1991
we choose the place, where the deflection is zero, i.e at
the point of contra flexure. otherwise it`s leads to collapse
| Is This Answer Correct ? | 18 Yes | 2 No |
Answer / ashutosh
in the design of RCC beam we design it as a crack section neglecting the area of concrete below the neutral axis so we can make a hole in concrete in the area below the neutral axis .
| Is This Answer Correct ? | 1 Yes | 1 No |
how much dry volume of cement in 1cum in m20 grade
Dear sir, i want to NBCC & NTPC previous exam papers email Id : madhu_bingi@yahoo.co.in
what is meant by camber
Why do not use fly ash bricks for waterproofing.
why we used shahabad stone (ladi) in box type water proofing.what is the main roll of shahabad stone?
what is difference between long column and short column?
16 Answers L&T, Tomi Polytechnic,
What are the Types of foundation?
What is the cost difference between site mix and ready mix concrete per cubic meter
How many cum of 9.5mm stone in 1 ton ?
how to Concrete cubes testing curing time 7 days casting date 24.05.17 testing date ?
Is there any codal provision stating the actual diameter for chair bars?
difference b/w stress and strength
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)