Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


entry criteria and exit criteria for unit testing, integration
testing, system testing and uat



entry criteria and exit criteria for unit testing, integration testing, system testing and uat..

Answer / neethu sebastian

Entry criteria for unit test
1.) All the requirement and documents are reviewed, finalized and approved.
2.) Application development should be completed
3.) Test environment is ready
4.) UnitTest Framework must be ready (in case of automated unit testing)
5.) Unit testing tools like Rational Software, JavaScript Assertion Unit, CUT, Dotunit ...etc (if tools are using) must be installed and configured.
(** last 2 points are optional hence can be avoided in interviews)

Exit criteria for Unit testing
1.) All the Unit test cases are executed.
2.) All the defects are resolved.
3.) coding is completed
4.) Code optimization (removal of redundant code, labeling of codes, removal of unused labels, removal of warning ..etc) is completed.

Entry criteria for integration testing
1.) Unit test exit criteria must meet
2.) Test environment should be ready
3.) Integration plan should be ready.
4.) Each module must gone through unit testing before the integration process.

Exit Criteria for Integration testing
1.) Successful execution of the integration tests.
2.) All priority bugs are resolve and closed.


Entry criteria for System testing
1.) Successful completion of integration testing process.
2.) Priority bugs found during integration testing must be fixed and closed.
3.) System testing environment must be available.
4.) Test cases must be available to execute

Exit Criteria for system testing
1.) Successful execution of the system tests.
2.) All specified business and functional requirements must be met.
3.) Priority bugs have been fixed and closed.
4.) Systems compatibility must be tested on various platforms

Entry Criteria for acceptance testing
1.) Successful completion of system testing phase.
2.) Priority bugs found during previous testing activities must be fixed and closed.
3.) Functional and Business requirement must be met.
4.) Acceptance testing environment should be ready.
5.) Test cases must be available.

Exit Criteria of Acceptance testing
1.) Successful execution of the user acceptance tests.
2.) approval for test Closure
3.)All Business requirements must be fulfilled.
4.) No critical defects are left out.

Is This Answer Correct ?    0 Yes 0 No

Post New Answer

More Manual Testing Interview Questions

Non functional testing Examples ?

1 Answers   Stag Computers,


How will you teach internet to 90 year old women (Grandamma)..i want see the response of this question.This was one my inerview question.

4 Answers   ABSC, AppLabs,


any one can explain error guessing..?it depends on validation or functional testing? give one example ..?

3 Answers  


Tell me the test cases for a search and replace functionality in a microsoft document (.doc)?

3 Answers   Oracle,


What is the difference between volume and stress?

1 Answers  


Write Test cases on pen?

2 Answers   Cap Gemini, PanTerra,


Relative to other technical groups in the company? Relative to your staff?

0 Answers  


difference between web based server and client based server?

2 Answers  


Hi Im Swarupa I have 1 Year of exp in Software Testing.I was involved in manual testing of the applications.Pls let me know if you know abt any oppurtunities...Preferred location Hyderabad

1 Answers  


Diff. between STLC and SDLC?

18 Answers   MBT,


What is meant by Test Script. Example and Explanation on Test Script?Please Answer

2 Answers   TCS,


1.Difference between System Testing and UAT 2.Difference between Load, Stress, Volume and Performance Testing. 3.Difference Between Integration testing and System Testing 4.Difference between Bug and Defect 5.Difference between Use Case and Test Case 6.Difference between Test Plan and Test Strategy 7.Difference between Test Scenario and Test Case 8.Difference between SRS and FRS 9.What are the difference b/w client & server? 10.explain test case template? 11.explain test plan template? 12.explain testing process? 13.explain bug report template? 14.what is scenario? 15.what is criteria?What are test entry and test exit criteria? 16.what is test strategy? 17.what is baseline? 18.what is hotfix? 19.what is Inspection,Walkthrough,Review,Audits 20.what is Stress Testing,Volume Testing,Sanity Testing 21.what is QA and QC? 22.Explain V-Model and Stages? What is Adv And DisAdv? 23.What is Boundary Value Analysis? 24.What is Equivalence Partitioning? 25.What is Error Guessing ? 26.What is Cause Effect Graphing techniques? 27.What is Bug , Defect and Error? 28.How will you report the bug? 29.What are the different test deliverables? Which deliverable we need to submit at the end of testing? 30.What methodologies have you used to develop test cases? 31.How you will close the defect? 32.What is meant by the bug state "Reproduce"? 33.What is change request?How do you handle change requests ? 34.what type of documents do u prepare during testing? 35.what are the testing methodologies? 36.What is release notes? 37.what is Response Time? 38.What report u generate after completing testing? 39.What is Test Bed? 40.Example for a bug having high severity and low priority? 41.Give me examples for high priority and low severity defects?

9 Answers   Nous,


Categories