Entry criteria for unit test
1.) All the requirement and documents are reviewed, finalized and approved.
2.) Application development should be completed
3.) Test environment is ready
4.) UnitTest Framework must be ready (in case of automated unit testing)
5.) Unit testing tools like Rational Software, JavaScript Assertion Unit, CUT, Dotunit ...etc (if tools are using) must be installed and configured.
(** last 2 points are optional hence can be avoided in interviews)
Exit criteria for Unit testing
1.) All the Unit test cases are executed.
2.) All the defects are resolved.
3.) coding is completed
4.) Code optimization (removal of redundant code, labeling of codes, removal of unused labels, removal of warning ..etc) is completed.
Entry criteria for integration testing
1.) Unit test exit criteria must meet
2.) Test environment should be ready
3.) Integration plan should be ready.
4.) Each module must gone through unit testing before the integration process.
Exit Criteria for Integration testing
1.) Successful execution of the integration tests.
2.) All priority bugs are resolve and closed.
Entry criteria for System testing
1.) Successful completion of integration testing process.
2.) Priority bugs found during integration testing must be fixed and closed.
3.) System testing environment must be available.
4.) Test cases must be available to execute
Exit Criteria for system testing
1.) Successful execution of the system tests.
2.) All specified business and functional requirements must be met.
3.) Priority bugs have been fixed and closed.
4.) Systems compatibility must be tested on various platforms
Entry Criteria for acceptance testing
1.) Successful completion of system testing phase.
2.) Priority bugs found during previous testing activities must be fixed and closed.
3.) Functional and Business requirement must be met.
4.) Acceptance testing environment should be ready.
5.) Test cases must be available.
Exit Criteria of Acceptance testing
1.) Successful execution of the user acceptance tests.
2.) approval for test Closure
3.)All Business requirements must be fulfilled.
4.) No critical defects are left out.
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
What if the project isn’t big enough to justify extensive testing?
Why performance testing is performed? What are tools of performance testing?
what is the common in all s.o.p (standaed operating procedure)?
How is ‘build’ different from ‘release’?
If automating - what is your process for determining what to automate and in what order
Can anybody give me some tips on how to face telephonic interview and Write some expected telephonic questions as a 2+yr exp. in testing. Try to give Ques. that u already hv faced in telephone. Plz Help me out friends.
Hi, I am planing to give ISTQB - Foundation level exam. Can anyone forward the ISTQB materials at laxmi_002@rediffmail.com mail ID.
What is a maturity level?
Hello all, Can someone tell me what kind of questions i can expect from hiring manager along with two team members on final face to face interview for manual testing position.. I am switching from BA to QA as its better on benefits etc.. Thanks in advance
What are all the netwoking tools, hardware tools and software tools required for testing a web-based n client server applicatopn?
WHAT IS PROTOCAL TESTING..EXPLAIN? L2, L3 PROTOCALS TESTING MEANS WHAT?EXPLAIN BRIEFLY
What are the major components of Perf Test Report?
Hi, Anybody knows about Hexaware company..
What is the difference between load and stress testing?
Manual and automation how do they help in bringing out quality product? Explain?