If u have 60KVA UPS, than tell me how systems ( computers )
u may connect?

Answers were Sorted based on User's Feedback



If u have 60KVA UPS, than tell me how systems ( computers ) u may connect?..

Answer / bala

Consider
200 VA / System
60kva x 0.8 = 48 kva ( Efficiency =0.8 )
Calculation
= 48000/200 =240 workstation or system

Is This Answer Correct ?    12 Yes 0 No

If u have 60KVA UPS, than tell me how systems ( computers ) u may connect?..

Answer / muthuramn

u can connect upt o 240 system

Is This Answer Correct ?    8 Yes 2 No

If u have 60KVA UPS, than tell me how systems ( computers ) u may connect?..

Answer / i h rao

Computers are working on DC power supply. If the DC conversion if suitable for 60 cycles then there will be no problem. Normally, DC power supply units are designed for both 50 and 60 cycles. Cycles depend on the RPM of the Alternator. Less the RPM less the cycles.

Is This Answer Correct ?    0 Yes 0 No

Post New Answer

More Electrical Engineering Interview Questions

what is the calculation method to design core and winding of a 200kva 3phase distribution transformer?

0 Answers  


In n high voltage 11kv system What happened if 1 of CT cable (IDMT) loose.Will e/f or o/c trip.please explain detail

1 Answers  


what is the power factor of choke coil used in tubelight

12 Answers   Bajaj,


What is the purpose of earthing Truck ? How does it work for busbar and cables?

1 Answers  


what must be the mf for a meter with the following conditions. line ct ratio-100/1 line pt ratio- 220kv/110v meter pt ratio- 3X63.5V meter CT ratio- -/1 A

1 Answers  






How to find out damper winding failure for synchronous machine?

0 Answers  


freuency meter

1 Answers  


HOW TO SIZE THE TRANSFORMER OR WHAT ARE THE STEPS INVOLVED IN FINDING THE SIZE OF THE TRANSFORMER FOR GIVEN LOAD SAY 2000KW ?

1 Answers  


where can the transformer having vector group Yny0 be used??

0 Answers   GK Power, NEA, Petrotech,


what is isolation Transformer?

8 Answers   HP,


We are having a 2000KVA DG set. It trips with Over speed and Engne Hot when the mahine is stopped in full speed. How shall I analyse the block load and reverse power.Is the problem related to power factor. The machine which runs on this DG is having all Synchronous motors with incividual Drives.

1 Answers  


The rating of Transformer are 11KV, 22KV, 33KV instead of 10KV, 20KV & 30KV?

2 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4452)
  • Electrical Engineering Interview Questions Electrical Engineering (16638)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)