how material can be calculate for brick work in 1:6
Answers were Sorted based on User's Feedback
Answer / shraddha
assume volume of brick masonary=10m3
dry volume=35% more=3.5 cu.m.
1.volume of cement=(3.5/7)*1=0.5cu.m
2.volume of sand=0.5*6=3 cu.m
3.no.of bricks=(10/0.004)=2500 No's
Is This Answer Correct ? | 5 Yes | 9 No |
ONE PART OF CEMENT OR LIME & SIX PART OF FINE AGGREGATE.
Is This Answer Correct ? | 6 Yes | 21 No |
whats is difference between anchorage length and development length
What is chemical composion test
What do you mean by the word 'shear'?
how much cubic feet cement contain in one bag
What glue is least sticky?
what are some possible sources of error in the CBR test?
What is the shelf life of a refractory used in boiler furnace ?
What is OSHA compliance?
how many type of admixtures for water stored structure?
what is diff between auto level and dumpy level?
CAN WE ADD SOME EXTRA QUANTITY OF GYPSUM INTO CONCRETE? WHAT PERCENTAGE WE CAN ADD? WHAT IS THE EFFECT ON STRENGTH?
Minimum spacing of 2- bars in column, beam, slab