how material can be calculate for brick work in 1:6
Answer Posted / shraddha
assume volume of brick masonary=10m3
dry volume=35% more=3.5 cu.m.
1.volume of cement=(3.5/7)*1=0.5cu.m
2.volume of sand=0.5*6=3 cu.m
3.no.of bricks=(10/0.004)=2500 No's
| Is This Answer Correct ? | 5 Yes | 9 No |
Post New Answer View All Answers
In csae of hume pipes NP stands for Non Pressure bur what does it really mean?
How much is the cover for slab?
what is flashing?
a) we have 30nos., 300mm dia, 4m length double under reamed piles.calculate excavation quantity.b) tell concrete qty. also.
225 mm thick RCC slab, how many ton load slab can carry? for example if 33 ton truck loaded with soil, truck having 6 wheels. slab can take load or not? grade of concrete is M35 and slab design Fe500, slab desing one way slab.
how to check and keep control on the wastage of material at site
The largest size of paper used in plotter to print the drawing made by Autocad .
I want to know the material required per square foot in rcc roof. i.e. steel: kg/foot, cement/foot etc.
What is the Roll of Water Bonding under VDF road?
how to estimate material requirement for an area of house in square feet?
What is the Systematic Responsibility Site Engineer? Who are the above and under co-oridinating ? What is office & Site co-ordination of Site Engineer?
Technical Question of Civil Engineering
What are the strongest shapes in building?
Curing time for 1)R.C.C slab 2)B.W 3)Plastering
For fine aggregate which is most suitable River sand or crusher sand & why ?