in control valve is constructed as per API 6D or API 6A,
then which standard is used for fire testing of valve?.
Answer / mahesh
If Control valve is constructed as per API 6D pr API 6A then fire testing of valve shall be as per the ISO 10497 or API 607
| Is This Answer Correct ? | 1 Yes | 0 No |
if we put any thermocouple on a table in a room without any connection,what temperature should it show.
Sir, I want junior executive, Instrumentation question papaer for IOCL, Plz send to arabinda.ghosh83@gmail.com
What is hp & mp seperator .& what is its working principle ?
why does a transmitter o/o signal starts from 3-15psi or 4- 20mA?
what is pt100 RTD, and does 100 stands for
who's take first position in process in the timing of new installation flow transmitter and control vavle. give the answer with logical trick.
I installed the smartplant instrument v8, but can not be opened, that always said: "INTools 2007 hardlock no found". So Could you help me how to do for that?
HOW WE ARE DECIDING WHILE PROGRAMMING IN PID CONTROLLER THAT WE ARE USING HEATING OR COOLING???????
I am working in a process industry, in that there are several sections devided in the SCADA screens and individual sections may START independently. But sometimes i am facing problem i.e, if section 2 Stopped by the operator immediately Section 1 or Section 3 or Section 4 is getting stopped can you expain the reason behind this?
whatis range of marcury filled tempereture gague
TEMPERATURE VARIATION FOR FREQUENTLY.
how to trim the pressure transmitter ?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)