Please tell me how many bricks needed for 4.5" bricks per
m3(how to calculate this also), and outurn of mason. Thanks.
Answer Posted / haris iqbal
frist calculate total volume of your brick work
VOLUME OF TOTAL BRICK WORK= L*B*H
NO OF BRICKS = total volume of your brick work * 13.5(one
cubic feet of work requried 13.5 bricks including mortor)
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
std penetration resistance in very stiff clays lies bet 2 & 4 4 & 8 8 & 15 15 & 30
what is the use in canals of longitudinal drains and cross drains in lining areas?
Whats the meanig of ,'K' VALUE in the case of soil.....
How to estimate the shuttering material requirement for a slab and beam and shear wall..? Please send thumbrule to estimate material required ( Plywood, Ms plates, runners, acrospans, jacks)
sir i want to know that in L & T construction can we do our 6 months training proggramme cum placement???????
what is the specific gravity of rubble in plum concert
How much does it cost for a R.C.C cover slab of size (450mmX 600mmx 100mm) double rf net given in feets using hand mix concrete?
Basic questions of civil engineering
How to find weight of steel in kg if we know the area which is in m2? Following details are known to us, Area=125m² thk of slab=250mm Steel details:T12@200 PS:considering mesh top and bottom with X and Y direction
what is stressing
what is the water-cement ratio of mix design while 30mpa in 7 days?
Explain the mechanism of cavitations in pipes and drains?
how can we calculate steel value, depending on load
it is a corrected question." make a list of engineering property(properties) of soil.
can you mail me detailed procedure,entire syllabus and practice papers of mpsc civil engineering branch.I am in third year now