Please tell me how many bricks needed for 4.5" bricks per
m3(how to calculate this also), and outurn of mason. Thanks.

Answer Posted / haris iqbal

frist calculate  total volume of your brick work

 VOLUME OF TOTAL BRICK WORK=   L*B*H

 NO OF BRICKS = total volume of your brick work * 13.5(one

 cubic feet of work requried 13.5 bricks including mortor)

Is This Answer Correct ?    1 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

what is c4x light weight cement blocks

5156


For Wet Mix Mecadam design what is Optimum moisture content

1618


show answer/ calculate-1-2-4 ratio-concrete -cement-sand- metal-water - please brief calculation

1693


What is semirigid connections?

1637


how much repeitation for conventional and maivan formwork?

1591






How much area, in square meters, will one liter of paint cover if it is brushed out to uniform thickness of 600 microns?

6269


rate analysis for cement pointing 1:4 , for 100 sq m

3704


percentage of metal,clay or soil & water in water bond macadam roads to know the quantities for each in total volume of 11500 cubic meters

1646


what is cement wastage percentage in NHAI ROAD WORKS

1435


quantity of material needed for rubble stone masonry for 1:4 and 1:6

1232


TELL US ABOUT A TIME WHEN YOU FAILED TO MEET A DEAD LINE. WHAT WERE THE REPERCUSSIONS?

1705


Basic questions of civil engineering

1622


What is a bearing capacity of soil?

815


What is Base Shear ?

673


what is the soil bearing capacity for a 5 floor multistorey residential building and which type of soil ? what is plinth beam? in wall load calculation center to center column distance is considered or not/

1818