how much binding wire is reqd for 1 MT
Answers were Sorted based on User's Feedback
Answer / srinivas
6mm to 12mm - 10kg
16mm to 25mm - 6kg
32mm to 50mm - 4kg
wastage for cutting binding wire & fixing - 5%
Is This Answer Correct ? | 17 Yes | 12 No |
Answer / mohammed mohiddin
Approximately 1.5 to 2% of the steel weight
i.e, 15 - 20 kg
Is This Answer Correct ? | 3 Yes | 7 No |
Answer / parag
approximately 12.5 kgs per Mt for reiforcement and
shuttering work
Is This Answer Correct ? | 0 Yes | 7 No |
Method of findingthe dry ingredient quantity of 1 m3 concrete.
25 Answers Annai Infra Developers, GKC Projects Limited GKCPL, IRE, L&T, Mahle Filter Systems, NCC, PNRD, Rama, RCC, Shivani Agriculture, Sobha Developers, Suraj Constructions, TCL,
HOW TO CALCULATE THE CEMENT & SAND REQUIRED FOR 1SQM BLOCKWORK OF 200MM THICK?
what is zone a n zone b?why the spacing of ring in zone a less.n zone b high?
How to calculate construction cost of residential building in mumbai
what is the yield strength of M30 grade of concrete
why do you desire to change from your current position?
how to calculate water cement ratio?
6 Answers IVRCL, Saroj Group, Sobha Developers,
How you will differentiate in field between grade43 and grade53 catagory cement?
1 cft have 13.5 No of Bricks, can someone help me to answer me for it's mathematically proof?
what is the cover used for footings, columns, beams ??? why they differ & how they arrive??
what is the strength [final]of grade m 15 to m 45
how can can column be corrected when the design is not safe ? is the increasing the clearcover a solution?