How much wastage we considered for cement
Answer Posted / praman srivastava
the wastage for steel & cement for mainly consider for
handling , tranpotation & workmanship & in case of steel
wastage consider for cutting bending & scrap during
work.Approximate 3% wastage consider for above as per CPWD
Norm.
Is This Answer Correct ? | 44 Yes | 10 No |
Post New Answer View All Answers
what is the formula to find the sttel (bar)length in beam having bent up at l/4 t 45 degree & 60 degree.
How to find the cuplock pipe qty in staging for Minor bridge?
why should we use 20mm graded metal only in vrcc?why we shouldnot use 40mm metal?
What are the phases inspections are done by local authority while construction?
for G+2 residential building how much quantity of required in foundations,sub & superstructures per sq ft area
what is the name of shuttering oil used in oman
How much Tolerance factors like 1. brick work 2.plaster 3.painting 4.floor tiling 5.wall tiling 6.shuttering 7.concreting 8.steel
How to identify the vitrified tile and ceramic tile by observation only after executing the job.
What is the thickness of slab for 600 sq each) 2 slab construction. What should be the size of steel rod?
Define What is an ice dam sock?
What is the strength of cement?
difference between fc and fc'?
What is the use of mirror command?
As we know that steel is a tension member but why we are using STRUCTURE STEEL as a COLUMN (Without concrete) where column is a compression member and compression strength of steel is very low
how to find ssm in foundation?