1) what is the seewage discharge per person per day taken
for design purpose as per IS codes? 2) how to convert gauge
to MM like if we measure 18G as our door frame then how
much is it in MM ? 3) how much binding wire is required ti
tie 100kg steel ? 4) while making rings in steel
reinforcement , whether the corners of rings are deducted
to take out cutting length ? 5) how much carbon content
should be there in steel used for construction purpose? 6)
what are fe415 & fe 500 and which bars are used in general
civil works?
Answer / santosh singh
1) sewage discharge per person is 120 litres/day
2) 18 gauge = 1.210mm there is a chart i will be sending
you if u want just tell me your email id my email address
is santosh29civil@gmail.com
3) for 1 ton 9 to 13 kg of winding wire is required ie.
for 100kg you will need 1 kg winding wire approximately
4) no the cutting length of beam or column ring is
calculated by foll. formula
total cutting length of ring = 2( a + b )+ 24d
where a = long side of ring
b = short side of ring
d = diameter of bar
remember when a bar is bend by bar pipe the bar extends by
2d
5) not more than 5%
6)fe415 & fe500 are high yield tensile bars used in
construction also mils steel ie fe230 is used in
construction work.depending upon type of load & stress
designer chosses the types of bars ...ie fe415 & fe500 tor
bars are used as they are having high strengths
Is This Answer Correct ? | 9 Yes | 0 No |
waht is the range of compacting factor test result for good concreate?
why top layer of block work shoud be full size if any cut block adjustable than another layer?
how to take out quantity of steel used in column and beam?? what is standard formula for it???
Write short note on construction programme for pile foundation.
What is unit weight of normal concrete?
What quantity of 1.0 m3 bricks required?
What are the Types Of DPC and its Thickness used?
what is the procedure for batching plant calibration??????
Which is default or standard size of tiles used in dado bathroom
how much need sand and cement for 1 cft roof construction?
0 Answers Indus Valley Construction IVCC,
During reclamation how can the occurrence of mud waves can be rectified?
a revised estimate is prepared when the original estimate has exceed by more than 1 percent 2 10 18.40